Capital Project Delivery Lifecycle

Manage a construction project seamlessly from initial blueprint review and pre-construction bid...

Sessions
17
Steps
111
Last edited
Oct 25, 2026
Created by
Nova

About this process

A unified, end-to-end operational framework that guides construction projects seamlessly from initial blueprint review and pre-construction bid leveling through project management, field execution, and final financial closeout.

The process in detail

17 sessions · 111 steps
01

📅 Meetings-Notes

2 steps
  1. 1

    Meeting Notes.

  2. 2

    To-do list

Read the full text
1. Meeting Notes.
Add notes
2. To-do list
Add tasks
02

1. Blueprint & Document Review

8 steps

Review project drawing sets across Architectural, Structural, and MEP disciplines to uncover constructability clashes, missing engineering details, and dimensional gaps. Your input directly shapes the formal Pre-Bid RFI log and ensures zero unverified assumptions enter our bid estimates.

  1. 1

    Provide the complete drawing set (Architectural, Structural, MEP) and technical specifications.

  2. 2

    📥 Audit Drawing Set Completeness

  3. 3

    🔍 Identify Discipline Clashes & Discrepancies

  4. 4

    ⚠️ Evaluate Risk & Constructability Severity

  5. 5

    📝 Compile Pre-Bid RFI Package

  6. 6

    Schedule a meeting 🤝 MEETING 1: Constructability & Scope Review Meeting

  7. 7

    Send the Design Team a formal written request for clarification or approval of a proposed solution.

  8. 8

    📁 Publish Version-Controlled Drawing Register

Read the full text
1. Provide the complete drawing set (Architectural, Structural, MEP) and technical specifications.
Upload files or add links
2. 📥 Audit Drawing Set Completeness

Examine the tender package provided (step 1) to confirm all required sheets, disciplines, and engineering specifications are accounted for before starting detailed trade analysis.

Cross-reference your received file manifest against the drawing index on sheet G-001 or equivalent:

•Architectural (A-series): Floor plans, reflected ceiling plans (RCP), exterior elevations, wall sections, and architectural door/finish schedules.
•Structural (S-series): Foundation plans, framing layouts, structural steel details, slab penetrations, and general structural notes.
•Mechanical, Electrical, Plumbing (MEP / M-E-P-series): Single-line diagrams, duct routing, electrical panels, plumbing risers, and equipment schedules.
•Civil & Geotechnical (C-series): Site grading, utility connection points, stormwater controls, and soil bearing capacity notes.
•Project Manual / Specs: Division 01 general requirements through Division 33 utilities.

Upload the consolidated plan index or mark missing sheets and revisions that must be requested immediately (step 3).

Upload files or add links
3. 🔍 Identify Discipline Clashes & Discrepancies

Perform a structured cross-discipline overlay to identify spatial conflicts, misalignments, and constructability dead-ends between drawing sheets.

Examine high-risk interface points using this review framework:

•Structural vs. MEP: Identify HVAC ducts, sanitary waste lines, or domestic water mains routed through structural steel beams, shear walls, or load-bearing footings without engineered penetrations or sleeves.
•Architectural vs. Structural: Verify clear ceiling heights against structural depth, framing dimensions against masonry wall thicknesses, and stairwell headroom clearances.
•Architectural vs. MEP: Check reflected ceiling plans against diffuser and sprinkler head layouts, verify electrical panel clearances, and confirm mechanical louvers align with exterior elevations.
•Plan vs. Elevation / Section: Reconcile dimension strings across plan views against building heights and finish schedules.

Record each discovered clash or constructability issue as an individual entry. Detail the sheet numbers involved, specific grid coordinates, and the exact physical or dimensional conflict observed.

Add notes
4. ⚠️ Evaluate Risk & Constructability Severity

Classify the overall severity and commercial risk level of the plan discrepancies identified during the cross-discipline scan.

Evaluate which trade interfaces pose the highest financial or schedule exposure if left unaddressed prior to bid closure:

•Structural load or footing dimension ambiguity that impacts concrete yardage.
•MEP spatial clashes requiring custom fabricated offsets or rerouting through tenant spaces.
•Missing manufacturer specifications for long-lead equipment or specialty architectural finishes.

Vote on the risk posture of the current drawing set and state in the comment which specific trade area carries the highest exposure.

Choose one
  • 🟢 Low Risk: Minor cosmetic or notes clarifications only
  • 🟡 Moderate Risk: Dimensional discrepancies solvable via standard details
  • 🔴 High Risk: Severe structural or MEP spatial clashes requiring engineering redesign
  • 🛑 Critical Blocker: Missing core engineering sheets preventing accurate estimating
  • ⚪ Zero Risk: Complete set verified, no RFIs required
5. 📝 Compile Pre-Bid RFI Package

Convert every documented drawing conflict, missing specification, and dimensional ambiguity into formal, contractual Pre-Bid Requests for Information (RFIs).

In commercial general contracting, our standard is zero bid-day assumptions. Every ambiguity must be framed with a specific question and a recommended contractor solution to expedite the architect or engineer's response.

Format your pre-bid RFI entries using this standard structure:

1.RFI Number & Trade Discipline: (e.g., RFI-01 — Structural / HVAC Interface)
2.Drawing & Spec References: Sheet numbers, grid locations, detail bubbles, and spec section codes.
3.Problem Statement: Concise explanation of the clash, missing dimension, or conflicting instruction.
4.Proposed Contractor Recommendation: A viable, cost-effective field solution that maintains building code compliance and design intent.

Draft each formal Pre-Bid RFI below so they can be merged directly into the master submission log for the design team.

Upload files or add links
6. Schedule a meeting 🤝 MEETING 1: Constructability & Scope Review Meeting

The Estimator, Lead Project Manager, and Field Superintendent gather to review the plan set together. The Superintendent brings real field experience (e.g., "We can't get a crane in here" or "This wall detail clashes with the steel HVAC duct"), which completes the list of RFIs before anything is finalized.

Choose one
  • 🟢 Meeting Completed — Plan Review Finished (Notes Captured in Session)
  • 🟡 In Progress — Individual Review Complete, Team Meeting Scheduled
  • ⚪ Skipped — Minor Project / Repeat Plan Set (PM/Estimator Sign-off Required)
  • 🔴 Blocked — Missing Key Drawings / Unresolved Design Clashes
7. Send the Design Team a formal written request for clarification or approval of a proposed solution.

Send the Design Team (the Architect, Structural Engineer, or MEP Engineer, depending on who produced the specific drawing) a formal written request for clarification or approval of a proposed solution. This resolves drawing discrepancies, missing dimensions, or physical conflicts before construction or pricing moves forward. Update the status when the request is sent and when the response is received.

Choose one or more
  • 📤 Sent
  • 📥 Received — Under Review
  • 🔄 Received — Revisions Needed
  • ✅ Approved — Proceed
8. 📁 Publish Version-Controlled Drawing Register

Establish the final baseline drawing repository and register to ensure all estimating estimators and bidding trade partners work from the exact same validated set.

Structure the baseline register with the following mandatory parameters:

•Document ID & Discipline: Drawing sheet number and trade category.
•Current Revision Level & Date: Explicit revision stamp (e.g., Rev 2 — Issued for Addendum 1, dated MM/DD/YYYY).
•Associated RFIs: Cross-reference active pre-bid RFI numbers tied to each specific sheet.
•Repository Link & Cloud Folder: Verified file path in the centralized document management environment.

Create a folder for this project. Upload the finalized Drawing & Addendum Log, add it to the folder, and link the version-controlled repository below to release the master set for quantity take-offs.

Upload files or add links
03

2. Quantity Take-Off & Scope Breakdown

10 steps

Complete the trade-by-trade quantity take-off and scope breakdown from the approved drawing set. You will apply CSI MasterFormat cost codes, calculate net quantities with explicit waste and contingency factors, establish crew productivity hours, and compile the final take-off schedule.

  1. 1

    🔗 Master Project Excel Workbook & 2D Drawing Folder: Add Link Below

  2. 2

    Calculate Net Trade Quantities

  3. 3

    Assign CSI MasterFormat Codes

  4. 4

    Apply Waste and Contingency Factors

  5. 5

    🔒 Stage Gate 1: Quantity & CSI Code Verification (Manager Review)

  6. 6

    Calculate Crew Labor Productivity Hours

  7. 7

    Flag High-Risk and Long-Lead Items

  8. 8

    Compile Final Scope Breakdown Schedule

  9. 9

    🔒 Stage Gate 2: Master Scope & Budget Approval (Final Gate)

  10. 10

    🔒 Stage Gate 2- Request 2: Master Scope & Budget Approval (Final Gate)

Read the full text
1. 🔗 Master Project Excel Workbook & 2D Drawing Folder: Add Link Below

Estimators will keep a 2D PDF drawing reader (like Bluebeam Revu or PlanSwift) open on one screen to measure dimensions, while having the Excel master estimating sheet open on their second screen to calculate line-item costs, labor hours, waste factors, and risk contingencies. Add both links here.

Upload files or add links
2. Calculate Net Trade Quantities

Extract primary geometric measurements directly from the current drawing set across all primary trade packages. Measure physical dimensions without adding hidden buffers or unit price inflation.

Use the standard geometric measurement units by trade:

•Division 03 Concrete: Volume in cubic yards (CY) = (Length in ft × Width in ft × Thickness in ft) / 27.
•Division 05/06 Framing & Lumber: Linear feet (LF) for plates and joists; board feet (BF) or member counts for studs; square footage (SF) for structural sheathing.
•Division 09 Finishes: Wall and ceiling surface area in square footage (SF), deducting rough door and window openings exceeding 10 SF.
•Divisions 22, 23 & 26 (MEP): Linear feet (LF) for major pipe runs, duct mains, and electrical home runs; discrete unit counts (EA) for panels, fixtures, junction boxes, and equipment drops.

Enter your net take-off quantities grouped by trade package. Note the drawing sheet references (e.g., A-101, S-201, E-002) used for each measurement.

Choose one
  • 🔴 Blocked — Missing Blueprint Sheets / Unreadable Plans
  • 🟠 High Variance — Scale Discrepancy Found in Drawings
  • 🟡 In Progress — Awaiting Missing Architectural / Structural Detail
  • 🟢 Quantities Measured — Ready for CSI Coding
3. Assign CSI MasterFormat Codes

Organize each measured scope item into its standardized 6-digit CSI MasterFormat division and cost code. Standardized cost coding ensures flawless bid-leveling and seamless export into your project accounting software.

Map your scope entries to these common standard divisions:

•03 30 00: Cast-in-Place Concrete (slabs, footings, grade beams)
•04 20 00: Unit Masonry (CMU walls, brick veneer)
•05 12 00: Structural Steel Framing (beams, columns, lintels)
•06 11 00: Wood Framing & Rough Carpentry
•07 21 00: Thermal Insulation
•08 11 00: Metal Doors and Frames
•09 22 00: Supports for Plaster and Gypsum Board (metal studs)
•09 29 00: Gypsum Board (drywall assemblies, taping, finishing)
•22 10 00: Plumbing Piping and Pumps
•23 31 00: HVAC Ducts and Casings
•26 05 00: Common Work Results for Electrical (conduit, wire, devices)

Enter each scope item with its assigned 6-digit CSI code, trade description, and total net unit quantity.

Choose one
  • 🔴 Blocked — Scope Description Ambiguous / Undefined Material
  • 🟠 Unmatched Code — Missing Division Category in Accounting System
  • 🟡 Pending Classification — Non-Standard / Custom Specialty Scope Item
  • 🟢 CSI Codes Mapped — Standard Divisions Complete
4. Apply Waste and Contingency Factors

Apply standard scrap and installation waste factors explicitly to your net measurements rather than padding labor rates or raw material costs. Never conceal contingency within base line items.

Use these industry standard waste formulas:

•Gross Material Quantity Formula: Gross Qty = Net Quantity × (1 + Waste Percentage)
•Ready-Mix Concrete (Footings/Slabs on Grade): Add 5% to 8% for spillage, over-excavation, and subgrade variance.
•Lumber & Light Gauge Framing: Add 8% to 10% for cuts, end-trimming, and blocking.
•Drywall & Sheathing Boards: Add 10% to 12% for cutting around openings, corners, and drop-off scrap.
•Piping, Conduit & Wiring: Add 5% to 7% for box drops, bends, elbows, and joint cuts.
•Overall Unforeseen Take-Off Contingency: Apply a baseline 3% to 5% line item contingency across the complete trade division package.

Select the contingency and waste protocol that best reflects the geometric complexity and site conditions of this project scope.

Choose one
  • 🟢 Standard Geometry & Tight Specs (3% Contingency, 5-8% Trade Waste)
  • 🟡 Moderate Cutting & Irregular Layouts (4% Contingency, 8-10% Trade Waste)
  • 🟠 Complex Architectural Plan / Heavy Waste (5% Contingency, 10-12% Trade Waste)
  • 🔴 High-Variance / Incomplete Details (5% Contingency + RFI Verification Required)
5. 🔒 Stage Gate 1: Quantity & CSI Code Verification (Manager Review)

Gate check before senior estimators apply waste, labor hours, and pricing: Review previous steps.

Choose one or more
  • 🛑 Critical Error — Drawing Scale or Revision Mismatch
  • 🔄 Revisions Required — Re-check Measurements / Codes in Excel
  • ✅ Quantities & CSI Codes Verified — Proceed to Pricing
6. Calculate Crew Labor Productivity Hours

Convert gross material quantities into estimated labor man-hours using standard crew production rates. Accurate labor calculations prevent scope gaps when reviewing trade subcontractor proposals.

Apply the standard labor productivity formula:

•Labor Hours Formula: Total Man-Hours = Gross Quantity / Crew Daily Production Rate × Crew Size × 8 Hours
•Concrete Flatwork: 0.05 to 0.08 man-hours per SF (placing, screeding, finishing).
•Metal Stud Framing (Interior Non-Structural): 0.035 to 0.05 man-hours per SF of wall face.
•Drywall Hanging & Level 4 Finish: 0.025 man-hours per SF hung; 0.020 man-hours per SF finished.
•Branch Wiring & Conduit: 0.06 to 0.09 man-hours per LF installed.

Calculate and list the total estimated craft labor hours required for each CSI trade division based on your gross material take-offs.

Choose one
  • 🔴 Blocked — Missing Gross Material Quantities
  • 🟠 High Labor Risk — Complex Site Access / Overtime Expected
  • 🟡 Pending Verification — Non-Standard Crew Rate / Union Labor Review
  • 🟢 Labor Hours Calculated — Standard Production Rates Applied
7. Flag High-Risk and Long-Lead Items

Identify materials, custom fabrications, and imported finishes that present severe supply chain vulnerabilities or critical path schedule risks. Flagging these items during pre-construction ensures procurement begins immediately upon bid award.

Review your take-off against standard high-risk construction categories:

•Long-Lead Structural Steel: Custom fabricated trusses, heavy wide-flange beams (16–24 week lead times).
•Curtain Wall & Architectural Glazing: Custom extrusions, thermal insulated units, switchable privacy glass (14–20 week lead times).
•Primary Electrical Gear: Main switchgear, distribution panels, automatic transfer switches (24–52 week lead times).
•Custom Finishes & Imported Goods: European tile, custom millwork, specialty architectural lighting (12–18 week lead times).

Record each flagged item using this structure:

1.Item Name & CSI Division:
2.Estimated Procurement Lead Time (Weeks):
3.Critical Path Impact / Risk Level: High, Medium, or Low
4.Pre-Ordering or Mitigation Strategy: (e.g., early submittal approval, alternate domestic manufacturer, early procurement package)
Choose one
  • 🔴 Blocked — Lead Times Unconfirmed by Suppliers
  • 🟡 Alternate Vendor Needed — Substitution Required to Meet Schedule
  • ⚠️ High Risk Flagged — Critical Path Item (12–24+ week lead time)
  • 🟢 Risk Audit Complete — All Standard Lead Times (under 6 weeks)
8. Compile Final Scope Breakdown Schedule

Synthesize your calculations into the master Quantity Take-Off & Scope Breakdown Schedule. This document serves as the internal pricing baseline for issuing subcontractor bid packages and evaluating trade quotes.

Format your take-off schedule using this required five-column line item structure:

•CSI Code & Scope Description: (e.g., 03 30 00 Cast-in-Place Slab on Grade, 5" 3000 PSI)
•Net Measured Quantity: (e.g., 185 CY based on sheets S-101 and S-102)
•Waste Factor Applied & Gross Quantity: (e.g., 7% waste = 198 CY gross)
•Estimated Direct Labor Hours: (e.g., 220 man-hours)
•Risk Classification & Lead Time: (e.g., Low risk / 3-day supplier notice)

Publish the completed schedule in your note below to establish the baseline for subcontractor bid leveling and procurement tracking.

Choose one
  • 🔴 Blocked — Outstanding Line-Item Revisions
  • 🟡 Draft Complete — Minor Allowance Reconciliation Pending
  • 🚀 Schedule Fully Compiled — Ready for Final Master Gate
9. 🔒 Stage Gate 2: Master Scope & Budget Approval (Final Gate)
Choose one
  • ❌ Bid On Hold — Client Scope Pause / Project Delay
  • 🔄 Adjust Pricing / Contingencies — Send Back to Estimator
  • 🚀 Final Sign-Off — Approved to Release Package to Subcontractors
10. 🔒 Stage Gate 2- Request 2: Master Scope & Budget Approval (Final Gate)
Choose one
  • ❌ Bid On Hold — Client Scope Pause / Project Delay
  • 🔄 Adjust Pricing / Contingencies — Send Back to Estimator
  • 🚀 Final Sign-Off — Approved to Release Package to Subcontractors
04

3. Sub-Contractor Bid Solicitations

8 steps

Review trade solicitation packages, verify pre-bid site walk attendance, and level subcontractor quotes line by line. Identify scope gaps, reconcile inclusions and exclusions, and select the winning trade partners to protect project margin.

  1. 1

    Audit Trade Bid Solicitations

  2. 2

    Audit Trade Bid Solicitations: Overview

  3. 3

    Confirm Pre-Bid Walk Attendance

  4. 4

    Normalize Trade Scope Inclusions

  5. 5

    Compare Unit Rates and Labor

  6. 6

    Select Winning Trade Subcontractors

  7. 7

    🔒 STAGE GATE: Subcontractor Award Approval (Project Executive / Director Sign-off)

  8. 8

    Generate Subcontract Award Packages

Read the full text
1. Audit Trade Bid Solicitations

Before opening quotes, verify that every trade division solicited at least three qualified, vetted subcontractors. Construction risk escalates when single-sourcing trades or accepting bids from contractors without verified safety records and pre-qualification status.

Review your invitation list across key CSI MasterFormat divisions (e.g., Division 03 Concrete, Division 05 Metals, Division 09 Finishes, Division 22 Plumbing, Division 26 Electrical)

Add tasks
2. Audit Trade Bid Solicitations: Overview

Flag any division that has fewer than three committed bidders so estimating can solicit immediate backup coverage before the bid deadline.

Choose one
  • 🔴 Critical Non-Compliance — Unvetted/Unlicensed Subcontractors or Plan Version Mismatch
  • 🟠 Coverage Gap — Prequalified Bidders, but Fewer Than 3 Bids in Certain Trades
  • 🟡 Prequalification Pending — 3+ Bidders, but Safety/License/Bonding Docs Incomplete
  • 🟢 Fully Verified & Compliant — 3+ Bidders, All Prequalified, Identical Plans
3. Confirm Pre-Bid Walk Attendance

Subcontractors who do not physically inspect existing site conditions introduce unbudgeted change orders once work commences. A mandatory pre-bid site walk ensures trade leads inspect logistical constraints, staging limitations, utility access, and demolition boundaries.

Check site walk records against bidder submissions:

•Verify sign-in sheets for mandatory site visit attendance.
•Document critical site conditions raised by trades during the walk (e.g., tight laydown area, limited hoisting capacity, floor leveling variance).
•Confirm whether field observations required a formal pre-bid RFI or design addendum issued to all bidders.

Select the status of pre-bid site walk verification across all bidding trades.

Choose one
  • 🟢 All bidders attended and acknowledged site conditions
  • 🟡 Some bidders missed walk; supplemental walks or waivers required
  • 🔴 Critical trades missed walk; high risk of unforeseen condition claims
4. Normalize Trade Scope Inclusions

Raw quote totals are deceptive because subcontractors frequently exclude necessary support work. Level each trade quote line by line against the defined Scope of Work package to establish true baseline comparisons.

Examine quotes across these recurrent scope gap zones:

•Waste and Disposal: Who provides and pays for dumpsters, trash chutes, and daily site clean-up?
•Hoisting and Rigging: Is crane service, telehandler access, or interior vertical transport included or excluded?
•Protection of Work: Who protects finished surfaces, adjacent trades, and weatherproof barriers?
•Temporary Utilities: Are task lighting, temp generators, water connections, and temp heat provided by the trade or the GC?
•Permits and Engineering: Are delegated engineering calculations (e.g., fire sprinkler calcs, truss engineering, storefront wind loads) included?

Draft the trade scope reconciliation matrix below. Note every item one bidder included that another excluded, along with the estimated plug number needed to balance them.

Upload files or add links
5. Compare Unit Rates and Labor

When base bids look competitive, differences in labor composition, shift premiums, and unit change-order rates can erode profit margins during construction.

Add tasks
6. Select Winning Trade Subcontractors

Select the approved trade partner award recommendation based on fully leveled comparisons, scope completeness, safety qualifications, and confirmed schedule commitments.

*Choose and option & add note: Choose the contracting recommendation status for this package and detail the winning subcontractors with agreed contract values in your rationale.

Choose one
  • 🏆 Award to primary low leveled bidder (all scopes confirmed)
  • ⚖️ Award to higher bidder due to schedule and qualification advantages
  • 🔄 Re-scope and re-solicit specific trade division before award
7. 🔒 STAGE GATE: Subcontractor Award Approval (Project Executive / Director Sign-off)
Choose one
  • 🛑 Rejected — Select Alternate Subcontractor
  • 🔄 Revisions Required — Re-level Trade Bids or Renegotiate Pricing
  • ⚠️ Approved with Conditions — Proceed with Value Engineering / Scope Adjustments
  • 🚀 Approved — Issue Subcontract Award Package
8. Generate Subcontract Award Packages

Compile the finalized subcontractor selection sheet into binding award packages to prepare for project buyout and subcontract drafting.

Your award summary must detail:

•Selected subcontractor business name and primary contact.
•CSI trade code and contracted scope description.
•Final negotiated base contract value and accepted alternate items.
•Locked schedule milestones (start date, duration, completion gate).
•Explicit inclusions and required submittals (cut sheets, shop drawings, insurance certs).

Document the finalized trade awards below. This log serves as the direct handover to project management for contract issuance and procurement tracking.

Upload files or add links
05

4. Proposal Generation & Client Contract Signing

9 steps

Compile and review the final cost structure, establish finish allowance schedules, and finalize the binding construction proposal for client execution. Use this session to verify margin protection, secure contract sign-off, confirm deposit receipt, and initiate permit registration.

  1. 1

    Proposal Generation & Client Contract Draft

  2. 2

    📊 Document the compiled cost summary below, listing direct hard costs, general conditions, contingency, and net margin percentage.

  3. 3

    🏷️ List all finish allowance categories below with their respective dollar limits and labor scope parameters.

  4. 4

    🗓️ Outline the major milestone target dates and critical path assumptions to be embedded directly into Exhibit B of the Prime Contract.

  5. 5

    🔍 Audit Margin and Contract Risks

  6. 6

    📄 Finalize Prime Contract Package

  7. 7

    ✍️ 📥 Download & Review: Download and review the attached Prime Contract Package and project proposal.

  8. 8

    ✍️ Track Contract Execution and Permitting

  9. 9

    📋 Transition to Project Setup

Read the full text
1. Proposal Generation & Client Contract Draft

[Get access to the main folder here]

Add tasks
2. 📊 Document the compiled cost summary below, listing direct hard costs, general conditions, contingency, and net margin percentage.
Write a note
3. 🏷️ List all finish allowance categories below with their respective dollar limits and labor scope parameters.
Write a note
4. 🗓️ Outline the major milestone target dates and critical path assumptions to be embedded directly into Exhibit B of the Prime Contract.
Write a note
5. 🔍 Audit Margin and Contract Risks

Perform an internal executive pre-issuance check to verify that contract language, escalation clauses, and margin boundaries meet company risk guidelines.

Review the proposed terms against these four non-negotiable protections:

•Price Escalation Clause: Material price fluctuation threshold (e.g., price swings exceeding 5% adjust contract sum).
•Payment Terms & Retainage: Clear billing milestone schedule (AIA G702/G703 format) with net 15 payment turnaround.
•Delay Conditions: Exclusions for delays caused by municipality permitting, utility providers, or client-driven material selection stalls.
•Change Order Protocol: Mandatory written authorization and prepaid administrative fee before any non-contract work begins.

Vote on the risk readiness of the proposal package and record any required contract stipulations.

Choose one
  • 🟢 Approved without modifications: contract margins and terms are protected
  • 🟡 Conditional approval: requires tightened allowance caps or escalation language
  • 🔴 Hold issuance: pricing gaps, low margin threshold, or unmitigated risk identified
6. 📄 Finalize Prime Contract Package
Add tasks
7. ✍️ 📥 Download & Review: Download and review the attached Prime Contract Package and project proposal.

Please review the attached Prime Contract Package below. Once approved, download the document, sign it, and re-upload the signed copy to formally finalize the contract and authorize project mobilization.

Choose one
  • Approve
  • Request changes
  • Decline
8. ✍️ Track Contract Execution and Permitting

Confirm formal execution of the Prime Contract, verify receipt of the initial project mobilization deposit, and launch the municipal permit application.

Follow this checklist to confirm the transition from pre-construction to active project management:

•Execute mutual signatures on the Prime Contract and all attached exhibits.
•Verify receipt and clearance of the initial client mobilization deposit (typically 10%–20%).
•Submit completed architectural, structural, and MEP drawing sets to the local building department for plan check review.
•Log municipal permit tracking number and assign initial field mobilization prep.

Confirm the execution status by selecting the appropriate stage below, adding the deposit receipt reference and permit tracking ID in your comments.

Choose one or more
  • ☑️ 📝 Contract fully executed by client and GC
  • ☑️ 💵 Initial mobilization deposit received and cleared
  • ☑️ 🏛️ Building permit application submitted to municipality
  • ☑️ 🚀 All execution gates closed: ready for Department 2 Project Setup
9. 📋 Transition to Project Setup

Deliver the final handoff plan transitioning the executed contract into Department 2: Project Management (Project Setup & Sub-Contractor Contracting).

Summarize the four core handoff parameters based on the executed agreement:

1.Locked Contract Value & Margin Target: Final agreed contract sum and baseline margin percentage to build cost codes in the project management software.
2.Sub-Contractor Buyout List: Confirmed leveled trade bids to convert immediately into standard sub-contractor agreements.
3.Key Allowance Dates: Priority selection deadlines that need client distribution within the first 14 days.
4.Permit Status & Planned Mobilization Date: Expected plan approval timeline and site fence installation date.

Record the transition summary below as the official baseline for the Project Setup session.

06

5. Project Setup & Sub-Contractor Contracting

5 steps

Review and execute the sub-contractor contracting and compliance gate for this project. You will lock in baseline CSI budget codes, verify executed trade agreements with required legal clauses, and validate active Certificates of Insurance and safety plans before authorizing site access.

  1. 1

    📊 Lock Baseline Cost Codes

  2. 2

    📝 Audit Sub-Contractor Agreement Clauses

  3. 3

    🛡️ Verify COIs and Endorsements

  4. 4

    👷 Enforce Safety Compliance Policies

  5. 5

    🛑 Issue Site Mobilization Clearances

Read the full text
1. 📊 Lock Baseline Cost Codes

Convert the winning estimate into active project cost codes to establish your baseline budget before commitments are issued.

Ensure each line item matches the standard CSI MasterFormat division structure, and verify that indirect general conditions and contingency accounts are isolated from direct trade labor and material lines.

Review the budget conversion rules:

•Direct Trade Codes: Map every winning sub-contractor award to its specific 6-digit CSI code (e.g., 03-30-00 Cast-in-Place Concrete, 26-00-00 Electrical).
•Contingency Separation: Never distribute GC contingency into trade budget lines; maintain contingency in an unallocated control code.
•Profit & Overhead Segregation: Verify that gross margin is locked in a separate financial control line so trade variances do not blur project markup.

Confirm that all line items match the signed Prime Contract Schedule of Values, and select the status that reflects your budget setup.

Choose one
  • 🟢 Baseline cost codes locked and balanced
  • 🟡 Minor cost code adjustments pending
  • 🔴 Estimate-to-budget variances require correction
2. 📝 Audit Sub-Contractor Agreement Clauses

Examine every Sub-Contractor Agreement draft against our mandatory project terms before sending out for execution.

A valid agreement protects project margin, guarantees delivery milestones, and enforces statutory compliance. Verify that each contract contains these essential exhibits:

•Schedule & Liquidated Damages: Baseline trade start and completion dates, milestone handoffs, and daily delay penalty language.
•Payment & Retainage Terms: Standard 10% retainage withholdings, 30-day pay-when-paid progress billing cycles, and requirement for conditional lien waivers with each invoice.
•Change Order Protocol: Explicit clause stating no additional field work or overtime will be compensated without a prior, written, GC-authorized Change Order.
•Scope Alignment: Referenced drawings with revision dates matching the Prime Contract exhibit list.

List any customized trade inclusions, exclusions, or modified contract terms for each critical trade partner. React with 👍 once each trade package is ready for signing.

Add notes
3. 🛡️ Verify COIs and Endorsements

Inspect incoming Certificates of Insurance (COI) from each trade partner against our standard contract limits and underwriting standards.

A missing endorsement exposes the general contractor to direct liability claims. Check each certificate against this risk matrix:

1.Commercial General Liability: Minimum $1,000,000 per occurrence / $2,000,000 aggregate.
2.Additional Insured Endorsements: Explicitly naming both the General Contractor and the Project Owner on form CG 20 10 (ongoing operations) and CG 20 37 (completed operations), or equivalent.
3.Workers' Compensation: Statutory limits with a formal Waiver of Subrogation in favor of the GC.
4.Automobile & Umbrella Liability: $1,000,000 combined single limit and $2,000,000 to $5,000,000 umbrella depending on trade risk tier.

Upload the verified COI documents, endorsements, and preliminary lien waivers here.

Upload files or add links
4. 👷 Enforce Safety Compliance Policies

Validate trade partner safety submissions to ensure complete OSHA alignment prior to site mobilization.

Zero tolerance applies to high-risk trades operating without validated training certifications or site-specific safety plans. Review each submission for:

•Site-Specific Safety Plan (SSSP): Highlighting specific trade hazards (fall protection, trenching, hot work, scaffolding).
•Safety Data Sheets (SDS): Digital chemical inventory submitted for centralized job site binder.
•Key Personnel Certifications: OSHA 30-hour certification for trade foremen and equipment operating licenses (forklift, aerial lift, crane).
•Sub-Contractor Safety Policy Sign-Off: Signed acknowledgement of the GC's zero-tolerance safety infractions and PPE requirements.

Rate the readiness of incoming trade safety programs using the options below.

Choose one
  • 🟢 Fully compliant with all certifications and signed policies
  • 🟡 Conditional approval pending specific equipment certifications
  • 🔴 Non-compliant: missing safety plan or signed acknowledgment
5. 🛑 Issue Site Mobilization Clearances

Execute the final readiness gate to authorize or deny site mobilization for each contracted trade partner.

Enforce the ironclad project rule: No trade partner steps foot on site without an executed agreement, verified active insurance, and a signed safety policy.

Assign the definitive onboarding clearance actions to the project team for site operations handoff.

Add tasks
07

6. Client Material & Finish Selection Management

10 steps

Review and lock in all client finish and fixture selections against project allowances and lead-time cutoff dates. You will curate spec options, track cost deltas, log physical sample approvals, and trigger purchase orders before fabrication deadlines impact the master schedule.

  1. 1

    🗓️ Map Selections Schedule & Cutoff Gates

  2. 2

    Create a document with a calendar schedule showing the deadlines for when decisions need to be made.

  3. 3

    Next steps

  4. 4

    Draft Curated Finish Options & Insert Portfolio Links

  5. 5

    Present Curated Options for Client Review & Link Selection

  6. 6

    Finalize Selection & Approve Option (Upgraded Option — B or C)

  7. 7

    Finalize Selection & Approve Option (Baseline Option — A)

  8. 8

    Next steps

  9. 9

    ✍️ Secure Material Selection Sign-Off

  10. 10

    🚀 Issue Procurement Purchase Orders

Read the full text
1. 🗓️ Map Selections Schedule & Cutoff Gates

Establish lead-time cutoff dates for every finish and fixture category by working backward from site installation milestones on the master schedule.

Use this backward-scheduling formula:

Cutoff Date = Installation Date - (Supplier Lead Time + Shipping/Customs Buffer + Job Site Acclimatization)

Standard trade benchmark buffers:

•Plumbing rough-in & trim: 6 to 10 weeks prior to framing closeout or tile installation
•Custom cabinetry & millwork: 10 to 14 weeks prior to finish carpentry
•Tile, slab & hard flooring: 6 to 8 weeks prior to scheduled wet trade start
•Lighting & low-voltage fixtures: 4 to 6 weeks prior to final drywall closure and trim-out
•Appliance packages: 8 to 12 weeks prior to kitchen cabinet delivery

Document the finish packages, their target delivery dates, supplier lead times, and client decision cutoff gates.

Write a note
2. Create a document with a calendar schedule showing the deadlines for when decisions need to be made.

Also add a table indicating the GC/Project Manager calculates the "drop-deadline date" (Cutoff Gate) by which a material must be chosen so it arrives on-site on time.

Upload files or add links
3. Next steps
Add tasks
4. Draft Curated Finish Options & Insert Portfolio Links

Provide a curated proposal featuring Option A, along with Option B or Option C. Option A must strictly align with the original contract budget allowance previously established. Options B and C represent upgrades or alternative specifications; simply include the direct links to each option package.

Upload files or add links
5. Present Curated Options for Client Review & Link Selection

Review the curated options provided below:

•Option A: Fits within the agreed contract budget allowance.
•Options B & C: Represent upgrades or alternative finish packages.

To review the full specifications for any package, click the corresponding link.

Choose one
  • Option A (Baseline): [ NAME ] [Trade & Cost Code]
  • Option A (Baseline): [ NAME ] [Trade & Cost Code]
  • Option A (Baseline): [ NAME ] [Trade & Cost Code]
6. Finalize Selection & Approve Option (Upgraded Option — B or C)

Return to the previous step and uncheck any options that were not chosen. Ensure only your single, final selection remains marked as selected.

You have selected an upgraded package (Option B/C). By approving this selection, you acknowledge and accept responsibility for the projected budget overage resulting from this choice.

Choose one
  • Approve
  • Request changes
  • Decline
7. Finalize Selection & Approve Option (Baseline Option — A)

Return to the previous step and uncheck any options that were not chosen. Ensure only your single, final selection remains marked as selected.

You have selected the baseline package (Option A). By approving this selection, you confirm that your contract budget allowance remains unchanged.

Choose one
  • Approve
  • Request changes
  • Decline
8. Next steps
Add tasks
9. ✍️ Secure Material Selection Sign-Off

Indicate the client approval status for the presented finish schedules, specification cut sheets, and material cost deltas.

Selecting an option confirms whether the material specifications have received binding client authorization to proceed into procurement:

•Approving with signature locks in all specifications, confirms allowance deltas, and authorizes immediate supplier purchase order commitments.
•Conditional approval requires minor finish or shade adjustments that do not alter core dimensions, rough-ins, or procurement lead times.
•Rejection or reselection triggers a mandatory schedule impact notice, revising the master milestone installation dates accordingly.

State the specific package approved and note any agreed cost adjustments in the comment field.

Choose one
  • ✅ Approved with signed cut sheets & cost deltas
  • ⚠️ Conditionally approved pending final dye lot/shade verification
  • 🔄 Re-selection requested (schedule impact notice issued)
  • ❌ Rejected by client
10. 🚀 Issue Procurement Purchase Orders

Execute vendor purchase orders, lock in committed shipping dates, and update material tracking logs to eliminate site mobilization delays.

Execute the following actions:

Add tasks
08

6.1 Change Order & Financial Management

7 steps

Log field scope deviations and client alteration requests, calculate true cost and schedule impacts, and generate the formal Change Order package. Use this workflow to eliminate verbal authorizations and secure binding client approval and payment terms before any extra work begins.

  1. 1

    📋 Classify Scope Deviation Origin

  2. 2

    🔍 Attach all supporting files inside this folder.

  3. 3

    💰 Calculate True Cost Delta

  4. 4

    ⏱️ Quantify Critical Path Schedule Impact

  5. 5

    📄 Generate Formal Change Order Package

  6. 6

    🚫 Enforce Authorization Protocol

  7. 7

    🚀 Release Execution & Subcontractor Directives

Read the full text
1. 📋 Classify Scope Deviation Origin

Identify the trigger and root cause behind the proposed change order. Accurate classification ensures proper risk allocation, contractual entitlement, and transparent client communication.

Review the situation against standard construction categories:

•Client-Requested Modification: Elective aesthetic, functional, or specification changes outside the executed Prime Contract.
•Unforeseen Site Condition: Concealed subsurface conditions, structural conflicts uncovered during demolition, or differing physical site conditions not shown on contract drawings (Type I or Type II site conditions).
•Design Discrepancy / Plan Clash: Omissions, conflicts between architectural and MEP drawings, or missing engineering details requiring design team clarification.
•Regulatory / Inspector Mandate: Municipal code enforcement corrections or updated utility company requirements issued after permit approval.

Select the origin category and record the specific drawing sheet, RFI reference, or site incident in the comments.

Choose one
  • 🎨 Client-Requested Modification
  • 🕳️ Unforeseen Concealed Site Condition
  • 📐 Plan Discrepancy / Design Conflict
  • 🏛️ Municipal Code / Inspector Mandate
2. 🔍 Attach all supporting files inside this folder.

🔍 Detail Field Scope & Site Evidence: Document the exact physical scope of work required and attach substantiating field documentation. Zero unverified claims are permitted. Upload photos showing clear scale (tape measure or reference object in view), marked-up drawing redlines, engineer field reports, or inspector notice slips.

Upload files or add links
3. 💰 Calculate True Cost Delta

Build the complete financial calculation for the proposed change order. Never bury contingency inside unit prices; show transparent line-item pricing across all direct and indirect expense categories.

Apply this General Contractor pricing structure:

1.Subcontractor / Trade Direct Costs: Hard quotes from each affected trade specifying labor hours, hourly trade rates, and raw material quantities with delivery fees.
2.GC Direct Labor & Supervision: Dedicated field superintendent hours required specifically for this alteration.
3.Equipment & Temporary Facilities: Specialized equipment rental, scaffolding, haul-away dumpsters, or temp power.
4.Contractual Overhead & Profit (O&P): Contractually established GC markup percentage applied to direct subtotal (typically 10% Overhead, 5% Profit or as specified in the Prime Contract).
5.Permits & Insurance / Bond Delta: Incremental insurance surcharge or municipal revision filing fees.

Log the calculated line-item breakdown, sub-tier quotes, and the net lump-sum change to the contract value.

Add notes
4. ⏱️ Quantify Critical Path Schedule Impact

Determine whether this change directly affects the project critical path or can be absorbed within available float. Adding work without updating calendar duration compromises milestone delivery dates.

Evaluate the schedule delta using this calculation checklist:

•Submittal & Engineering Lead Time: Required turnaround time for revised shop drawings, structural calculations, or municipal plan revisions.
•Material Procurement & Delivery Lead Time: Custom fabrication lead times or shipping transit delays for newly specified materials.
•Physical Installation Duration: Trade crew sequencing, cure times (e.g., concrete/grout), and mandatory pre-concealment municipal inspections.
•Net Critical Path Shift: Number of work days added to the Substantial Completion date after evaluating logic ties and available schedule float.

Select the schedule impact bracket that applies to this change order and state the exact net calendar day adjustment in the comments.

Choose one
  • ⚡ 0 Days (Absorbed by Float / Parallel Task)
  • 📅 1 to 5 Calendar Days Added
  • 🗓️ 6 to 15 Calendar Days Added
  • 🚨 16+ Calendar Days Added (Critical Delay)
5. 📄 Generate Formal Change Order Package

Compile the official General Contractor Change Order document (such as standard AIA Document G701 or company Master Agreement format) for distribution.

The change order package must strictly contain:

•Sequential Number & Title: Clear project numbering (e.g., CO #04 - South Footing Undermining Rework).
•Scope Summary: Plain-language description of additions, deletions, and trade scope modifications.
•Financial Reconciliation: Original contract sum, previous authorized changes, current change amount, and revised total contract sum.
•Contract Time Reconciliation: Original substantial completion date, previous adjustments, net calendar days added, and new legally binding completion date.
•Payment Terms: Required deposit percentage (e.g., 50% upon execution for custom procurement) or inclusion in the next regular progress billing application.

Upload the finalized change order PDF document ready for client review.

Upload files or add links
6. 🚫 Enforce Authorization Protocol

Enforce the project-wide "Zero Verbal Change Orders" policy. No field superintendent, trade foreman, or project manager may instruct trade crews to commence unapproved extra work based on verbal agreements or text messages.

Before releasing work in the field, verify that all four mandatory authorization criteria are satisfied:

1.Client Signature: Legally authorized representative has executed the formal Change Order document.
2.Schedule Acceptance: Client has formally acknowledged the revised substantial completion date.
3.Deposit or Billing Alignment: Advance deposits for long-lead materials collected, or line item integrated into the Schedule of Values.
4.Trade Subcontract Revision: Written work authorization or subcontract change order issued to trade partners locking their price and scope.

Confirm the authorization status of this change order. Selecting fully authorized releases field execution.

Choose one
  • 📝 Draft / Under Internal Review
  • ⏳ Pending Client Signature & Deposit
  • ✅ Fully Executed (Authorized to Proceed)
  • ❌ Rejected / Scope Abandoned
7. 🚀 Release Execution & Subcontractor Directives

Once authorization is confirmed, transition the change order from commercial management into active field operations. Assign clear owners and deadlines to prevent operational friction.

Create specific tasks to complete the change order rollout:

•Issue Subcontractor Change Order (SCO) to trades
•Update Master Schedule with new critical path dates
•Update Schedule of Values for next progress billing
•Conduct site briefing with trade superintendents

Assign each task to the responsible project manager or field superintendent with firm completion dates.

Add tasks
09

🔄 8. Progress Billing & Application for Payment

6 steps

Execute the monthly client progress billing workflow by auditing on-site progress against the Schedule of Values, reconciling trade pay applications and lien waivers, and compiling the AIA G702/G703 billing package. Submit the complete application with photographic backup for architect certification and client disbursement.

  1. 1

    Audit Physical Progress Against SOV

  2. 2

    Reconcile Subcontractor Applications & Waivers

  3. 3

    Upload Progress Photos & Delivery Slips

  4. 4

    Compile AIA G702 & G703 Application Package

  5. 5

    Verify Billing Quality & Compliance Gates

  6. 6

    Approve & Issue Payment Package

Read the full text
1. Audit Physical Progress Against SOV

Conduct the end-of-month physical progress walk across all active trades to confirm percentage-of-completion before drafting billing figures.

Evaluate physical work in place against the approved Schedule of Values (SOV) line items. Overbilling without field verification triggers architect rejections, pencil-copy disputes, and cash flow delays.

Apply standard progress calculation logic:

•Work Completed to Date: Calculate actual installed physical quantities or milestones completed per line item.
•Materials Stored On-Site: Verify that billed materials are securely delivered, inspected for damage, and properly inventoried. Do not bill off-site materials without formal client/lender authorization and bonded warehouse documentation.
•Retainage Calculation: Apply the contractually stipulated retainage rate (typically 5% or 10%) uniformly across completed work and stored materials.

Mark the audit status for each trade phase to ensure complete field alignment prior to compiling pay applications.

Choose one or more
  • ✅ Field progress verified against SOV line items
  • ⚠️ Discrepancy noted between trade claim and physical installation
  • 📦 Stored materials inspected and documented on site
  • 🔄 Pencil copy draft reviewed with Project Superintendent
2. Reconcile Subcontractor Applications & Waivers

Review each active trade contractor's monthly payment application against inspected field progress and verify legal compliance documents.

Never advance a subcontractor billing line into the prime billing package without verifying both the math and statutory lien releases:

•Verify claimed labor and material percentages against your superintendent's field audit notes.
•Ensure the current gross billing minus retainage matches the net amount requested.
•Collect a fully executed Partial Conditional Lien Waiver covering the exact gross amount claimed for the current billing cycle.
•Confirm receipt of an Unconditional Lien Waiver covering the prior month's disbursed funds.

Record any required downward adjustments or missing lien waivers in the log below so adjustments can be reflected on the draft G703.

Add notes
3. Upload Progress Photos & Delivery Slips

Attach date-stamped photographic evidence and delivery documentation supporting every major progress milestone claimed this cycle.

Architects, owners' representatives, and bank draw inspectors require clear visual proof before certifying payment applications:

•Upload high-resolution photos organized by SOV line item or division showing completed rough-ins, finishes, or structural assemblies.
•Include clear photos of staging areas for billed stored materials, showing weather protection and manufacturer labels.
•Attach freight bills of lading and supplier delivery tickets for high-value raw material drops.

Add all supporting visual documentation and delivery slips here.

Upload files or add links
4. Compile AIA G702 & G703 Application Package

Assemble the formal AIA Document G702 (Application and Certificate for Payment) and AIA Document G703 (Continuation Sheet).

Verify the core accounting reconciliation across all summary lines on the G702 summary page:

•Line 1 (Original Contract Sum): Must match prime contract base value.
•Line 2 (Net Change Orders): Reflects all mutually executed change orders through the billing cut-off date. Do not bill pending or verbal changes.
•Line 3 (Contract Sum to Date): Line 1 plus/minus Line 2.
•Line 4 (Total Completed & Stored to Date): Sum of Column G from the G703 Continuation Sheet.
•Line 5 (Retainage): Calculated precisely according to contract percentages (Work in Place retainage + Stored Materials retainage).
•Line 6 (Total Earned Less Retainage): Line 4 minus Line 5.
•Line 7 (Less Previous Certificates for Payment): Line 6 from the immediately preceding certified pay app.
•Line 8 (Current Payment Due): Line 6 minus Line 7.
•Line 9 (Balance to Finish, Including Retainage): Line 3 minus Line 6.

Upload the compiled draft PDF of the G702 and G703 forms, accompanied by the notarized signature sheet.

Upload files or add links
5. Verify Billing Quality & Compliance Gates

Execute the final quality control gate to verify that every legal, mathematical, and contractual requirement is fulfilled prior to release.

Work through the standard GC payment compliance checks:

•Arithmetic verified: Column totals on G703 balance across columns C, D, E, F, G, H, and I.
•Executed change orders only: Zero unapproved or pending scope adjustments included.
•Notarization: G702 contractor declaration properly signed and notarized by an authorized officer.
•Subcontractor lien documentation: Current conditional releases and prior unconditional releases gathered and filed.
•Stored material receipts: Supported by insured site verification or bonded off-site certificates.

Confirm each verification item below.

Choose one or more
  • 🧮 G702 and G703 mathematical reconciliation confirmed
  • 📝 Notarized contractor signature executed on G702
  • 📑 All active trade conditional lien waivers collected
  • 📸 Photographic audit package attached to submittal
  • 📋 Change order summary aligns with executed contract modifications
6. Approve & Issue Payment Package

Authorize the final submission of the monthly Application and Certificate for Payment to the Project Architect and Client.

Review the assembled package:

•Executed AIA G702 and G703 Continuation Sheets
•Schedule of Values line-by-line reconciliation
•Supporting photo log and material delivery receipts
•Prime Contractor Conditional Lien Waiver

Approve to release the official draw submittal to the design team and ownership, or decline with specific correction notes regarding discrepancies in SOV percentages, lien documentation, or calculations.

Choose one
  • Approve
  • Request changes
  • Decline
10

Milestone 1: Site Mobilization & Safety Setup

6 steps

Verify jobsite infrastructure, establish safety and environmental controls, and conduct the trade orientation kickoff. Complete these verification steps to authorize heavy equipment delivery and initial trade crew mobilization.

  1. 1

    Verify Temporary Utilities & Site Infrastructure

  2. 2

    Audit Environmental Controls & Stormwater

  3. 3

    Post OSHA Signage & Safety Stations

  4. 4

    Document Trade Superintendent Kickoff Meeting

  5. 5

    Execute Pre-Mobilization Action Items

  6. 6

    Authorize Site Mobilization & Trade Access

Read the full text
1. Verify Temporary Utilities & Site Infrastructure

Establish physical perimeter control and temporary utility connections before allowing field operations to commence.

Inspect each infrastructure element against local municipal building codes and OSHA standards:

•Perimeter & Security: Chain-link security fencing installed, gated access points established, sightline screens secured, and emergency vehicle clearance verified.
•Temporary Power: Temporary electrical service drop inspected and energized, GFCI-protected distribution panels installed, and spider boxes placed clear of transit paths.
•Temporary Water & Sanitation: Backflow-prevented construction water source tapped, freeze protection wrapped if applicable, and serviced portable chemical toilets placed on a 1:10 worker ratio with handwashing stations.
•Traffic & Staging: Crushed rock tracking pad (stabilized construction entrance) installed to prevent mud tracking, delivery drop zones demarcated, and trade parking designated.

Select your current infrastructure verification status and note any utility provider lead times or inspection delays.

Choose one
  • 🏗️ All Utilities & Security Fencing Active
  • ⏳ Pending Utility Meter Connection
  • ⚠️ Fencing or Sanitary Incomplete
  • 🛑 No Site Infrastructure In Place
2. Audit Environmental Controls & Stormwater

Review and activate the project's Stormwater Pollution Prevention Plan (SWPPP) and site environmental mitigation controls.

Ensure all mandated regulatory safeguards are active prior to earthwork or site disturbance:

•Sediment & Erosion Controls: Silt fencing trenched at least 6 inches deep with stakes on the downslope, wattles installed along curb lines, and gravel bag check dams secured.
•Inlet Protection: Geotextile fabric or filter inserts installed in all adjacent street storm drain basins and municipal catch basins.
•Concrete Washout: Lined, watertight concrete washout pit or prefabricated container positioned with high-visibility signage away from natural drainages.
•Dust & Track-Out Prevention: Water truck or misting hookup ready for active ground disruption, with sweeping protocol established for municipal rights-of-way.

Document any field variances or municipal SWPPP permit conditions that require daily logging.

Write a note
3. Post OSHA Signage & Safety Stations

Verify all mandatory federal, state, and local safety compliance stations are mounted and accessible across the field office and jobsite entry gates.

Inspect against this life-safety standard:

1.Compliance Board: State and federal labor law posters, OSHA Job Safety and Health Protection poster, and the emergency evacuation route map posted under weather protection.
2.Safety Data Sheets (SDS): Central yellow SDS binder compiled with manufacturer safety sheets for all initial chemical products, adhesives, and fuel sources on site.
3.Emergency Medical Stations: Fully stocked ANSI Class B first aid kit mounted, eyewash station tested, and secondary bloodborne pathogen response kit verified.
4.Perimeter Warning Signage: High-visibility PPE requirements posted at all gate entries (Hard Hats, High-Vis Vests, Safety Glasses, Steel-Toe Boots Mandatory Beyond This Point).
5.Fire Protection: Inspected, tagged 10-pound 2A:10B:C dry chemical fire extinguishers placed every 3,000 square feet and within 50 feet of any flammable storage or hot work area.

Indicate compliance status for site life-safety setup.

Choose one
  • 🦺 100% OSHA Signage & Medical Stations Ready
  • 📋 SDS Binder or Posters Pending Update
  • 🧯 Fire Extinguishers / First Aid Deficient
  • 🛑 Safety Compliance Walk Failed
4. Document Trade Superintendent Kickoff Meeting

Conduct the mandatory on-site mobilization kickoff meeting with all contracted trade superintendents, foremen, and project engineers.

Walk through these critical coordination topics:

•Working Hours & Noise Ordinances: Define daily start/stop times (e.g., 07:00 to 15:30), quiet hours, and weekend work restrictions.
•Access & Deliveries: Publish delivery booking windows, crane pick areas, laydown allocations, and clean-as-you-go trash removal mandates.
•Daily Safety Protocols: Mandatory morning Toolbox Talks submission schedule, daily sign-in rosters, hot work permits, and zero-tolerance drug/alcohol enforcement.
•Incident Escalation: Chain of command for immediate reporting of near-misses, injuries, structural damage, or municipal stop-work notices.

Log the meeting minutes, record attending trade companies and superintendents, and list all agreed jobsite logistics agreements here.

Write a note
5. Execute Pre-Mobilization Action Items

Complete all assigned operational tasks before clearing subcontractors to bring machinery or full labor crews onto the site.

Assign specific team owners and firm due dates to ensure zero regulatory or physical bottlenecks remain.

Add tasks
6. Authorize Site Mobilization & Trade Access

Issue the formal determination on site readiness for full trade mobilization.

Review the preceding verifications: temporary utilities energized, perimeter secured, SWPPP sediment controls trenched, OSHA compliance stations mounted, and trade kickoff orientations conducted.

Select the authorized site access level. Use the comment box to specify any conditional holdbacks (e.g., Site cleared for framing and excavation crews; mechanical rough-in staging restricted until east laydown pad gravel cures).

Choose one
  • 🟢 Full Mobilization Authorized (Unrestricted Site Access)
  • 🟡 Conditional Mobilization (Specific Trades Only)
  • 🔴 Site Mobilization Denied (Safety / Utility Hold)
11

Milestone 2: Daily Execution & Quality Assurance Inspections

5 steps

Log your daily field operations, morning safety briefings, trade inspections, and photo documentation directly in this session. Your submissions create the verified chronological record of job site progress, subcontractor quality control, and pre-concealment sign-offs.

  1. 1

    🦺 Conduct Morning Toolbox Talk

  2. 2

    📋 Log Daily Site Conditions & Headcounts

  3. 3

    🔍 Audit In-Progress Trade Work

  4. 4

    📸 Verify Pre-Concealment Photo Records

  5. 5

    📌 Execute Daily Field Closeout Tasks

Read the full text
1. 🦺 Conduct Morning Toolbox Talk

Run the mandatory morning safety and production stand-up with all active trade foremen prior to work commencing.

Brief the specific high-risk operations scheduled for today (such as hot work, overhead lifting, trenching, or leading-edge fall protection), verify required Personal Protective Equipment (PPE) compliance across all crews, and confirm site logistics including crane delivery staging and material drop zones.

Select the primary safety focus addressed during this morning's briefing:

Choose one or more
  • 🦺 Fall Protection & Scaffolding
  • ⚡ Electrical Safety & Lockout/Tagout
  • 🚜 Trenching, Excavation & Heavy Equipment
  • 🔥 Hot Work, Fire Watch & Burn Permits
  • 🧤 PPE, Silica Dust & Chemical Handling
  • 📦 Overhead Hazards, Rigging & Crane Logistics
2. 📋 Log Daily Site Conditions & Headcounts

Record the official job site operational parameters to establish a verifiable legal and contractual record of daily site activity.

Capture the following operational baseline:

•Weather and site conditions: Note ambient temperature highs/lows, precipitation, wind conditions, and any adverse impacts to exterior operations (such as slab pours or roofing).
•Subcontractor trade headcounts: Document each trade contractor present on site along with the exact number of journeymen and apprentices deployed (e.g., Framing: 8, Electrical: 4, Plumbing: 3).
•Major deliveries & heavy equipment: Record bulk material deliveries received, ticket numbers, crane hours, lifts, or excavators active on site.
•Milestone progress: Detail the primary production accomplishments completed across building zones.

Provide your comprehensive daily operational notes below.

Write a note
3. 🔍 Audit In-Progress Trade Work

Inspect ongoing trade work against approved construction submittals, architectural and structural drawings, and manufacturer installation specifications.

Evaluate current installations across these core quality dimensions:

1.Dimensional tolerance: Verify rough opening clearances, wall plumbness, slab elevations, and sleeve locations.
2.Material compliance: Confirm that installed fixtures, rebar sizing, fasteners, insulation types, and pipe schedules match approved submittal cut sheets.
3.Manufacturer specifications: Check adherence to environmental requirements (such as curing temperature, sealants, lap splices, and mechanical fastening patterns).

Identify any deviations, non-conforming items, or defective workmanship. Record the trade responsible, grid line or room location, specific code/plan discrepancy, and the mandatory corrective action required within 24 hours.

Add notes
4. 📸 Verify Pre-Concealment Photo Records

Capture photographic proof of all mechanical, electrical, plumbing, structural framing, and waterproofing work before it is permanently concealed by insulation, drywall, backfill, or concrete pours.

High-resolution pre-concealment documentation prevents future warranty disputes and provides clear evidence of code compliance for municipal building inspectors and owners.

Upload clear photos of all in-wall rough-ins, above-ceiling mechanical rough-ins, under-slab conduits, and waterproofing membranes prior to sign-off. Ensure photos capture room markers, grid references, and backing plates.

Upload images
5. 📌 Execute Daily Field Closeout Tasks

Complete the end-of-day site protocol to ensure physical security, environmental compliance, and complete accountability before trade crews depart the property.

Assign and verify the mandatory end-of-day site handover items:

Add tasks
12

📅 1.1. Meeting: Constructability & Scope Alignment

7 steps

Review and evaluate physical site logistics, interdisciplinary drawing clashes, schedule lead times, and environmental safety hazards (as a team: Estimator, PM, Superintendent) to align on site logistics, crane access, and drawing clashes before publishing the RFI package and before committing estimating resources. Work through each critical section with the project team and select the constructability status for each domain. Use your findings to resolve the final Master Gate decision to release, condition, or hold the estimating workflow. If this project qualifies for an expedited path, select Skipped and provide the operational justification below. [ Add link to main folder with documents here]

  1. 1

    🏗️ Evaluate Site Logistics & Access

  2. 2

    📐 Screen Drawing Clashes & Scope Gaps

  3. 3

    ⏱️ Assess Phasing, Schedule & Long-Lead Items

  4. 4

    🦺 Identify Safety & Hazardous Conditions

  5. 5

    Other Notes

  6. 6

    🚦 Resolve Master Gate Status

  7. 7

    Photos or files

Read the full text
1. 🏗️ Evaluate Site Logistics & Access

Evaluate whether physical equipment, materials, and crane operations can be mobilized without disrupting surrounding municipal traffic or adjacent operations. Review project boundaries, street widths, municipal right-of-way restrictions, and overhead utility lines against your proposed staging plan.

Focus your evaluation on these core logistics factors:

•Heavy equipment & hoisting: Crane setup footprint, swing radius restrictions, and external personnel/material hoist locations.
•Laydown & staging: On-site material drop zones versus off-site marshalling yards or scheduled just-in-time (JIT) deliveries.
•Delivery routes & curfews: Municipal lane closure permits, oversize transport corridors, and restricted delivery time windows.
•Utility connections: Clear access to municipal water, power ties, and civil shut-off points.

Select the current logistics status below, and log any required permit triggers or JIT delivery constraints in the comment field.

Choose one
  • 🟢 Logistics Cleared — Standard site access with no major physical constraints
  • 🟡 Tight Staging — Limited space; requires off-site storage or just-in-time deliveries
  • 🔴 High Risk / Restricted — Crane permits, road closures, or zero laydown space required
2. 📐 Screen Drawing Clashes & Scope Gaps

Examine interdisciplinary drawing alignment across Architectural, Structural, Civil, and MEP/FP sheets to isolate constructability conflicts before pricing.

Identify hard spatial clashes and ambiguous details that introduce bid scope gaps or change-order exposure during field execution.

Audit the drawing set against these common failure points:

•Vertical & horizontal clearances: Structural steel or deep transfer girders cutting through primary HVAC supply trunk lines or gravity drainage slopes.
•Shaft & riser coordination: Plumbing and electrical riser shafts aligning across floor plates without penetrating shear walls or rated corridors.
•Envelope & fire separation: Missing fire-rated partition details, ambiguous curtain wall anchorage, or incomplete waterproof flashing assemblies.
•Scope handoffs: Demarcation gaps between core-and-shell provisions and interior tenant fit-out systems.

Select the drawing risk classification below, and cite the specific drawing sheet numbers and conflicting details in your rationale comment.

Choose one
  • 🟢 Clean Drawing Set — Minor or no trade clashes identified
  • 🟡 RFIs Drafted — Clashes identified; preliminary pre-bid RFIs created for architect review
  • 🔴 Critical Redesign Required — Major structural or MEP conflict that blocks accurate estimating
3. ⏱️ Assess Phasing, Schedule & Long-Lead Items

Analyze whether baseline project milestones are achievable within existing lead times, site operating rules, and local jurisdictional ordinances.

Compare anticipated manufacturing and shipping cycles for critical-path equipment against the client's mandatory completion date.

Examine schedule integrity against these four operational parameters:

•Long-lead equipment: Switchgear, custom air handling units, chillers, structural steel packages, and specialized elevators requiring immediate pre-release or owner pre-purchase.
•Working-hour rules: City noise ordinances, night-shift premiums, weekend working allowances, or occupied-facility operational restrictions.
•Critical sequence logic: Concrete cure times, envelope dry-in prerequisites, and temporary power energization milestones.
•Weather & season risk: Substructure concrete pouring windows, freeze protection, or severe weather contingencies.

Select the schedule feasibility status below, and note all components whose fabrication cycles threaten the baseline delivery date.

Choose one
  • 🟢 Schedule Feasible — Standard construction sequence and lead times
  • ⚠️ Long-Lead Flagged — Critical path materials require early procurement or owner pre-purchase
  • 🔴 Schedule Compression Risk — Unrealistic timeline; liquidated damage exposure
4. 🦺 Identify Safety & Hazardous Conditions

Assess severe project safety risks, neighboring structural dependencies, and environmental contaminants that mandate specialized engineering controls or regulatory plans.

Review site soil reports, hazardous material surveys, and surrounding building alignments to prevent catastrophic field failures and regulatory stoppages.

Examine the scope against these specialized safety categories:

•Subsurface & civil risks: Deep foundation excavations, utility potholing/811 verification, tieback installation, and underpinning of adjacent foundations.
•Hazardous abatement: Encapsulation or licensed abatement for friable asbestos, lead-based paint, silica, or active fungal contamination.
•Fall protection & overhead hazards: Leading-edge tie-off engineering, high-rise perimeter netting, and swing-radius exclusion zones.
•Restricted access operations: Confined space entries, electrical flash boundaries, and structural demolition sequencing.

Select the safety classification below, and state any mandatory engineered safety plans, subcontractor certifications, or third-party monitoring requirements.

Choose one
  • 🟢 Standard Safety Risk — Baseline safety controls apply
  • 🟡 Specialty Safety Required — Deep excavations, confined spaces, or high-voltage work identified
  • 🔴 Environmental / Shoring Hazard — Hazardous abatement or complex structural shoring required
5. Other Notes
Add notes
6. 🚦 Resolve Master Gate Status

Consolidate the findings from all four constructability domains and render the binding Master Gate decision for this pre-construction milestone.

Review the prior sections: Logistics, Drawing Clashes, Schedule/Long-Lead, and Safety. Your selection governs whether the estimating team immediately advances to Quantity Take-Offs and scope breakdown, holds for critical engineering clarifications, or bypasses detailed review.

Evaluate the decision criteria:

•Approved: All sections are green. Proceed directly to trade package prep, take-offs, and formal pre-bid RFI issuance.
•Approved with Conditional RFIs: Manageable trade clashes or long-lead items identified. Proceed with take-offs while tracking active conditional RFIs.
•Skipped: Repeat prototype, direct replacement, or minor interior refresh where constructability risk is already established.
•Blocked: Critical redesign, unresolved structural conflict, or fatal logistics barrier that invalidates baseline estimating. Hold estimating immediately.

Select the overall Master Gate status below and state the binding operational rationale, including mandatory conditions or hold requirements.

Choose one
  • 🟢 Approved — Proceed to RFI Submission & Take-Offs
  • 🟡 Approved with Conditional RFIs — Proceed with Take-Offs
  • ⚪ Skipped — Minor Project / Repeat Prototype Plan
  • 🔴 Blocked — Hold Take-Offs Until Key RFIs / Redesigns Resolved
7. Photos or files
Upload files or add links
13

📅 3.1 Subcontractor Bid Leveling Alignment Meeting.

5 steps

Review and level trade subcontractor bids side-by-side with Estimating, Project Management, Procurement, and Field Operations. Reconcile scope inclusions and exclusions, evaluate bidder safety and schedule commitments, and formally authorize trade awards before issuing subcontract agreements. During the meeting, each team member brings their pre-meeting work to answer their specific part of the puzzle: Lead Estimator: Demonstrates whether the bid is financially balanced, covers the full CSI scope, and fits within the baseline estimate. Project Manager: Confirms if the subcontractor can meet the critical path schedule and hit key submittal deadlines. Procurement Specialist: Confirms if the bidder passed safety (OSHA), insurance, and bonding checks. Field Superintendent: Confirms whether the sub has the actual crew size and field logistics capability to pull it off on-site.

  1. 1

    📋 Does the selected subcontractor have a 100% complete scope with zero unassigned gaps, and are their prequalifications (safety, bonding, and capacity) fully verified?

  2. 2

    📋 Does this bid fit within the target budget and schedule milestones—and if selecting a non-cheapest bidder, what is the clear operational justification?

  3. 3

    Meeting Notes

  4. 4

    🚦 Establish Bid Leveling Status & Final Decision Log

  5. 5

    Subcontractor Award & Bid Leveling Decision Summary - Document

Read the full text
1. 📋 Does the selected subcontractor have a 100% complete scope with zero unassigned gaps, and are their prequalifications (safety, bonding, and capacity) fully verified?
•Confirms whether gray-area items (like scaffolding, hoisting, trash removal, and site cleanup) are accounted for or if they will turn into unbudgeted change orders later.
•Ensures the bidder isn't a liability risk regarding safety records (OSHA), licensing, or financial capacity to complete the job.
Choose one
  • 🔴 Scope Gaps Identified (Unassigned Line Items)
  • 🟡 Scope Complete (Pending Prequalification Docs)
  • 🟢 Scope Complete & Fully Prequalified
2. 📋 Does this bid fit within the target budget and schedule milestones—and if selecting a non-cheapest bidder, what is the clear operational justification?
•Confirms the subcontractor can meet key project dates without long-lead material delays.
•Directly captures why a team might award a contract to a trade partner who is $15,000 more expensive (e.g., guaranteed earlier start date, superior manpower, or lower quality risk).
Choose one
  • 🔴 Over Budget / Schedule Risk (Requires Re-Bidding or Value Engineering)
  • 🟡 Higher Bid Selected (Justification Documented)
  • 🟢 Lowest Qualified Bid (Within Budget & Schedule)
3. Meeting Notes
Add notes
4. 🚦 Establish Bid Leveling Status & Final Decision Log

Provide a brief summary in the comment box detailing the selected subcontractor, pricing tier, justification, and any open contingencies or immediate actions required before contract generation.

Copy, paste, and complete the template below into the session comment box:

TRADE DIVISION: 06-100 — Rough Carpentry / Framing

Selected Trade Partner: [ Apex Framing Co. ]

Pricing Tier: ( ) Lowest Bid (•) Higher-Priced Bid

Award Justification: Guaranteed 2-week faster schedule

Final Contract Value: $245,000.00

Choose one
  • 🟢 Bids Leveled & Selected — Ready for Award Approval
  • 🟡 Conditional Selection — Pending Final Scope / Price Clarification with Sub
  • 🟠 Scope Gap / Cost Overrun — Re-bidding or Value Engineering Required
  • 🔴 Blocked — Insufficient Prequalified Bidders (Fewer than 3 Bids)
5. Subcontractor Award & Bid Leveling Decision Summary - Document

Turn the notes from the final decision step into a 1–3 page document that includes the selected trade division and subcontractor, their pricing, justification, open contingencies, actions required before contract generation, and any notes worth considering during contract creation. Create a table.

Upload files or add links
14

📅 3.2 Executive Buyout & Risk Approval

2 steps

Review the compiled project estimate, risk contingency reserves, and prime contract legal liabilities with leadership and estimating. Verify margin thresholds and risk allocations to establish our final binding bid release decision. Required Attendees General Contractor Executive (VP of Operations / Owner / Managing Director) Chief Estimator Lead Project Manager Meeting objective: The objective is to get executive sign-off on the full project numbers before legally binding the company.

  1. 1

    Review the following documents

  2. 2

    🚦 Resolve Proposal Release Status

Read the full text
1. Review the following documents
•Master Pre-Construction Financial Summary (The Project "P&L")
•Subcontractor Award & Bid Leveling Decision Summary
•Risk Matrix & Contingency Allocation Log
•Prime Contract Terms & Conditions Highlights (Redline Review)

Find all documents below.

Upload files or add links
2. 🚦 Resolve Proposal Release Status

Select the formal executive resolution status for this project based on the margin verification, contingency audit, and contractual review.

What Gets Evaluated & Decided?

•Target Gross Margin Verification: Does the compiled estimate meet the GC's required profit margin percentage?
•Contingency Buffer & Financial Risk: Is the overall contingency buffer sufficient to cover long-lead price spikes, potential owner delays, or unassigned scope gaps?
•Contractual & Liability Review: Are liquidated damages, payment terms, retainage schedules, and owner contract liabilities acceptable to company leadership?

State the specific rationale, required financial or margin adjustments, and any mandatory contract riders directly in your selection comment:

Choose one
  • 🟢 Approved — Execute Prime Contract & Release Subcontracts
  • 🟡 Conditional Approval — Adjust Margin / Contingency & Re-Submit
  • 🔴 Rejected — High Financial Risk / Scope Overrun (Contract Holds Required)
15

📅 4.1 Internal Project Handoff Meeting

20 steps

The Estimator walks the operational team through the project scope, estimate, schedule baseline, and trade awards step-by-step. Who Attends: Lead Estimator, assigned Project Manager, assigned Field Superintendent, and (optionally) the Executive/Director. Create: Trande-by-trade package. Buyout & Handover Binder (or Digital Folder) organized by CSI MasterFormat divisions (e.g., Concrete, Framing, MEP, Finishes). For each trade division, the PM and Superintendent receive: The Winning Subcontractor Proposal: Final scope sheet and contract amount. The Bid Leveling Matrix: Showing all trade partners who bid, their side-by-side pricing, and why the winner was selected. Scope Boundary & Interface Notes: Explicit mentions of gray-area responsibilities (e.g., "Framing sub is responsible for layout; Drywall sub is responsible for daily jobsite trash removal"). Open Contingencies & Long-Lead Items: Outstanding prequalification items (like missing COIs or bonds) and material lead times that threaten the schedule

  1. 1

    Todays meeting: Select a trade.

  2. 2

    Package Handoff & Scope Briefing

  3. 3

    Package Handoff & Scope Briefing

  4. 4

    Package Handoff & Scope Briefing

  5. 5

    Package Handoff & Scope Briefing

  6. 6

    Package Handoff & Scope Briefing

  7. 7

    Package Handoff & Scope Briefing

  8. 8

    Package Handoff & Scope Briefing

  9. 9

    Package Handoff & Scope Briefing

  10. 10

    Package Handoff & Scope Briefing

  11. 11

    Package Handoff & Scope Briefing

  12. 12

    Package Handoff & Scope Briefing

  13. 13

    Package Handoff & Scope Briefing

  14. 14

    Package Handoff & Scope Briefing

  15. 15

    Package Handoff & Scope Briefing

  16. 16

    Package Handoff & Scope Briefing

  17. 17

    Package Handoff & Scope Briefing

  18. 18

    Package Handoff & Scope Briefing

  19. 19

    Package Handoff & Scope Briefing

  20. 20

    Generate PM & Superintendent Action Summaries

Read the full text
1. Todays meeting: Select a trade.

Package Handoff: [ Folder Link]

Select the trade to discuss today and verify that the final package transfer is complete. If any information is missing, note it below; outstanding details will be provided within 2 days.

Choose one or more
  • 🧹 01 00 00 — General Conditions & Site Logistics: Site cleanup, temporary utilities, dumpsters, and site security.
  • 🚜 02 00 00 — Sitework & Earthwork: Demolition, excavation, grading, utility trenching, and paving.
  • 🧱 03 00 00 — Cast-in-Place Concrete: Footings, foundation slabs, grade beams, and structural concrete pouring.
  • 🧱 04 00 00 — Masonry: CMU block walls, brick veneer, stone installation, and mortar work.
  • 🏗️ 05 12 00 — Structural Steel & Metals: Steel beams, columns, metal decking, stairs, and structural welding.
  • 🪵 06 11 00 — Framing & Rough Carpentry: Wood/metal stud framing, roof trusses, floor joists, and structural sheathing.
  • 🪴 06 20 00 — Finish Carpentry & Millwork: Interior trim, baseboards, custom cabinetry, doors, and hardware.
  • 🛡️ 07 21 00 — Thermal & Moisture Protection: Insulation, waterproofing, flashing, and roofing systems.
  • 🪟 08 50 00 — Doors, Windows & Glazing: Storefront glass, exterior windows, skylights, and door hardware.
  • 🦺 09 22 00 — Drywall & Gypsum Board: Wallboard installation, metal studs, taping, plastering, and joint finishing.
  • 🪨 09 30 00 — Tile & Stone: Ceramic, porcelain, stone flooring, splashbacks, and wet area waterproofing.
  • 🪵 09 64 00 — Hardwood & Resilient Flooring: Hardwood, LVT, vinyl, carpet, and subfloor prep.
  • 🎨 09 90 00 — Painting & Wallcoverings: Interior/exterior paint, primers, caulking, stains, and wall finishes.
  • 🚰 22 10 00 — Plumbing & Piping: Underground rough-in, gas lines, water pipes, drain systems, and fixtures.
  • ❄️ 23 31 00 — HVAC & Climate Systems: Ductwork, air handlers, condensers, exhaust fans, and thermostats.
  • ⚡ 26 05 00 — Electrical & Low Voltage: Main service panels, conduit, wiring, lighting fixtures, fire alarms, and data wiring.
  • 🚒 21 10 00 — Fire Suppression: Overhead sprinkler mains, drops, heads, and fire pump systems.
  • 🌳 32 90 00 — Landscaping & Irrigation: Planting, sod, irrigation lines, hardscaping, and site retaining walls.
2. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
3. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
4. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
5. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
6. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
7. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
8. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
9. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
10. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
11. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
12. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
13. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
14. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
15. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
16. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
17. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
18. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
19. Package Handoff & Scope Briefing

The Estimator delivers the complete estimating binder, master schedule, and baseline budget to the PM and Superintendent.

Choose one
  • 🔴 In Progress — Awaiting Final Package Transfer
  • 🟢 Complete — Handoff Package Received & Reviewed
20. Generate PM & Superintendent Action Summaries
1.Project Manager (PM) Document: Compile all logged notes, questions, or requests regarding contracts, budgets, change orders, and submittals into a dedicated PM summary. Include a section for general comments. If no relevant notes were recorded, omit this document.
2.Superintendent (SI) Document: Compile all logged notes, questions, or requests regarding site safety, daily schedules, quality assurance, and trade coordination into a dedicated Superintendent summary. Include a section for general comments. If no relevant notes were recorded, omit this document.
Upload files or add links
16

✅ 5.1 Permitting & Utility Checklist

1 step

Complete and track all mandatory site mobilization prerequisites including building permits, municipal approvals, temporary utility hookups, and subcontractor insurance coverage. Assign owners and confirm status before heavy equipment delivery or full field mobilization begins.

  1. 1

    ✅ Complete Site Mobilization Compliance Checklist

Read the full text
1. ✅ Complete Site Mobilization Compliance Checklist

Review and execute the mandatory compliance prerequisites required prior to authorizing full jobsite mobilization and equipment drop-off.

Unresolved jurisdictional approvals or missing utility interconnections create catastrophic delays, stop-work orders, and liability exposure. Verify each requirement against current project records:

•Building & Trade Permits: Confirm master building permit, grading/erosion control permits, and specialty trade permits (electrical, plumbing, mechanical) are physically posted on-site and active.
•Municipal & AHJ Sign-offs: Verify Department of Transportation right-of-way encroachment permits, curb-cut approvals, and local fire department emergency access and hydrant clearances.
•Temporary Utilities: Ensure temporary power service drops, temp electrical distribution boards, and temporary construction water meters/backflow preventers are inspected, energized, and functional.
•Insurance Compliance: Audit all mobilizing subcontractor Certificates of Insurance (COIs) to verify that the general contractor and project owner are named as additional insureds with active statutory workers' compensation, general liability, and auto coverage.

Check off each item, attach supporting documentation or inspection sign-offs directly to the task, and log any open compliance holds in the task notes.

Add tasks
17

5.2: Master Submittal & Shop Drawing Register