Project name

Sessions
17

The process in detail

01

📅 Meetings-Notes

2 steps
  1. 1

    Meeting Notes.

  2. 2

    To-do list

Read the full text
1. Meeting Notes.
Add notes
2. To-do list
Add tasks
02

🔄 Progress Billing & Application for Payment

6 steps

Execute the monthly client progress billing workflow by auditing on-site progress against the Schedule of Values, reconciling trade pay applications and lien waivers, and compiling the AIA G702/G703 billing package. Submit the complete application with photographic backup for architect certification and client disbursement.

  1. 1

    Audit Physical Progress Against SOV

  2. 2

    Reconcile Subcontractor Applications & Waivers

  3. 3

    Upload Progress Photos & Delivery Slips

  4. 4

    Compile AIA G702 & G703 Application Package

  5. 5

    Verify Billing Quality & Compliance Gates

  6. 6

    Approve & Issue Payment Package

Read the full text
1. Audit Physical Progress Against SOV

Conduct the end-of-month physical progress walk across all active trades to confirm percentage-of-completion before drafting billing figures.

Evaluate physical work in place against the approved Schedule of Values (SOV) line items. Overbilling without field verification triggers architect rejections, pencil-copy disputes, and cash flow delays.

Apply standard progress calculation logic:

•Work Completed to Date: Calculate actual installed physical quantities or milestones completed per line item.
•Materials Stored On-Site: Verify that billed materials are securely delivered, inspected for damage, and properly inventoried. Do not bill off-site materials without formal client/lender authorization and bonded warehouse documentation.
•Retainage Calculation: Apply the contractually stipulated retainage rate (typically 5% or 10%) uniformly across completed work and stored materials.

Mark the audit status for each trade phase to ensure complete field alignment prior to compiling pay applications.

Choose one or more
  • ✅ Field progress verified against SOV line items
  • ⚠️ Discrepancy noted between trade claim and physical installation
  • 📦 Stored materials inspected and documented on site
  • 🔄 Pencil copy draft reviewed with Project Superintendent
2. Reconcile Subcontractor Applications & Waivers

Review each active trade contractor's monthly payment application against inspected field progress and verify legal compliance documents.

Never advance a subcontractor billing line into the prime billing package without verifying both the math and statutory lien releases:

•Verify claimed labor and material percentages against your superintendent's field audit notes.
•Ensure the current gross billing minus retainage matches the net amount requested.
•Collect a fully executed Partial Conditional Lien Waiver covering the exact gross amount claimed for the current billing cycle.
•Confirm receipt of an Unconditional Lien Waiver covering the prior month's disbursed funds.

Record any required downward adjustments or missing lien waivers in the log below so adjustments can be reflected on the draft G703.

Add notes
3. Upload Progress Photos & Delivery Slips

Attach date-stamped photographic evidence and delivery documentation supporting every major progress milestone claimed this cycle.

Architects, owners' representatives, and bank draw inspectors require clear visual proof before certifying payment applications:

•Upload high-resolution photos organized by SOV line item or division showing completed rough-ins, finishes, or structural assemblies.
•Include clear photos of staging areas for billed stored materials, showing weather protection and manufacturer labels.
•Attach freight bills of lading and supplier delivery tickets for high-value raw material drops.

Add all supporting visual documentation and delivery slips here.

Upload files or add links
4. Compile AIA G702 & G703 Application Package

Assemble the formal AIA Document G702 (Application and Certificate for Payment) and AIA Document G703 (Continuation Sheet).

Verify the core accounting reconciliation across all summary lines on the G702 summary page:

•Line 1 (Original Contract Sum): Must match prime contract base value.
•Line 2 (Net Change Orders): Reflects all mutually executed change orders through the billing cut-off date. Do not bill pending or verbal changes.
•Line 3 (Contract Sum to Date): Line 1 plus/minus Line 2.
•Line 4 (Total Completed & Stored to Date): Sum of Column G from the G703 Continuation Sheet.
•Line 5 (Retainage): Calculated precisely according to contract percentages (Work in Place retainage + Stored Materials retainage).
•Line 6 (Total Earned Less Retainage): Line 4 minus Line 5.
•Line 7 (Less Previous Certificates for Payment): Line 6 from the immediately preceding certified pay app.
•Line 8 (Current Payment Due): Line 6 minus Line 7.
•Line 9 (Balance to Finish, Including Retainage): Line 3 minus Line 6.

Upload the compiled draft PDF of the G702 and G703 forms, accompanied by the notarized signature sheet.

Upload files or add links
5. Verify Billing Quality & Compliance Gates

Execute the final quality control gate to verify that every legal, mathematical, and contractual requirement is fulfilled prior to release.

Work through the standard GC payment compliance checks:

•Arithmetic verified: Column totals on G703 balance across columns C, D, E, F, G, H, and I.
•Executed change orders only: Zero unapproved or pending scope adjustments included.
•Notarization: G702 contractor declaration properly signed and notarized by an authorized officer.
•Subcontractor lien documentation: Current conditional releases and prior unconditional releases gathered and filed.
•Stored material receipts: Supported by insured site verification or bonded off-site certificates.

Confirm each verification item below.

Choose one or more
  • 🧮 G702 and G703 mathematical reconciliation confirmed
  • 📝 Notarized contractor signature executed on G702
  • 📑 All active trade conditional lien waivers collected
  • 📸 Photographic audit package attached to submittal
  • 📋 Change order summary aligns with executed contract modifications
6. Approve & Issue Payment Package

Authorize the final submission of the monthly Application and Certificate for Payment to the Project Architect and Client.

Review the assembled package:

•Executed AIA G702 and G703 Continuation Sheets
•Schedule of Values line-by-line reconciliation
•Supporting photo log and material delivery receipts
•Prime Contractor Conditional Lien Waiver

Approve to release the official draw submittal to the design team and ownership, or decline with specific correction notes regarding discrepancies in SOV percentages, lien documentation, or calculations.

Choose one
  • Approve
  • Request changes
  • Decline
03

1. Site Mobilization & Safety Setup

6 steps

Verify jobsite infrastructure, establish safety and environmental controls, and conduct the trade orientation kickoff. Complete these verification steps to authorize heavy equipment delivery and initial trade crew mobilization.

  1. 1

    Verify Temporary Utilities & Site Infrastructure

  2. 2

    Audit Environmental Controls & Stormwater

  3. 3

    Post OSHA Signage & Safety Stations

  4. 4

    Document Trade Superintendent Kickoff Meeting

  5. 5

    Execute Pre-Mobilization Action Items

  6. 6

    Authorize Site Mobilization & Trade Access

Read the full text
1. Verify Temporary Utilities & Site Infrastructure

Establish physical perimeter control and temporary utility connections before allowing field operations to commence.

Inspect each infrastructure element against local municipal building codes and OSHA standards:

•Perimeter & Security: Chain-link security fencing installed, gated access points established, sightline screens secured, and emergency vehicle clearance verified.
•Temporary Power: Temporary electrical service drop inspected and energized, GFCI-protected distribution panels installed, and spider boxes placed clear of transit paths.
•Temporary Water & Sanitation: Backflow-prevented construction water source tapped, freeze protection wrapped if applicable, and serviced portable chemical toilets placed on a 1:10 worker ratio with handwashing stations.
•Traffic & Staging: Crushed rock tracking pad (stabilized construction entrance) installed to prevent mud tracking, delivery drop zones demarcated, and trade parking designated.

Select your current infrastructure verification status and note any utility provider lead times or inspection delays.

Choose one
  • 🏗️ All Utilities & Security Fencing Active
  • ⏳ Pending Utility Meter Connection
  • ⚠️ Fencing or Sanitary Incomplete
  • 🛑 No Site Infrastructure In Place
2. Audit Environmental Controls & Stormwater

Review and activate the project's Stormwater Pollution Prevention Plan (SWPPP) and site environmental mitigation controls.

Ensure all mandated regulatory safeguards are active prior to earthwork or site disturbance:

•Sediment & Erosion Controls: Silt fencing trenched at least 6 inches deep with stakes on the downslope, wattles installed along curb lines, and gravel bag check dams secured.
•Inlet Protection: Geotextile fabric or filter inserts installed in all adjacent street storm drain basins and municipal catch basins.
•Concrete Washout: Lined, watertight concrete washout pit or prefabricated container positioned with high-visibility signage away from natural drainages.
•Dust & Track-Out Prevention: Water truck or misting hookup ready for active ground disruption, with sweeping protocol established for municipal rights-of-way.

Document any field variances or municipal SWPPP permit conditions that require daily logging.

Write a note
3. Post OSHA Signage & Safety Stations

Verify all mandatory federal, state, and local safety compliance stations are mounted and accessible across the field office and jobsite entry gates.

Inspect against this life-safety standard:

1.Compliance Board: State and federal labor law posters, OSHA Job Safety and Health Protection poster, and the emergency evacuation route map posted under weather protection.
2.Safety Data Sheets (SDS): Central yellow SDS binder compiled with manufacturer safety sheets for all initial chemical products, adhesives, and fuel sources on site.
3.Emergency Medical Stations: Fully stocked ANSI Class B first aid kit mounted, eyewash station tested, and secondary bloodborne pathogen response kit verified.
4.Perimeter Warning Signage: High-visibility PPE requirements posted at all gate entries (Hard Hats, High-Vis Vests, Safety Glasses, Steel-Toe Boots Mandatory Beyond This Point).
5.Fire Protection: Inspected, tagged 10-pound 2A:10B:C dry chemical fire extinguishers placed every 3,000 square feet and within 50 feet of any flammable storage or hot work area.

Indicate compliance status for site life-safety setup.

Choose one
  • 🦺 100% OSHA Signage & Medical Stations Ready
  • 📋 SDS Binder or Posters Pending Update
  • 🧯 Fire Extinguishers / First Aid Deficient
  • 🛑 Safety Compliance Walk Failed
4. Document Trade Superintendent Kickoff Meeting

Conduct the mandatory on-site mobilization kickoff meeting with all contracted trade superintendents, foremen, and project engineers.

Walk through these critical coordination topics:

•Working Hours & Noise Ordinances: Define daily start/stop times (e.g., 07:00 to 15:30), quiet hours, and weekend work restrictions.
•Access & Deliveries: Publish delivery booking windows, crane pick areas, laydown allocations, and clean-as-you-go trash removal mandates.
•Daily Safety Protocols: Mandatory morning Toolbox Talks submission schedule, daily sign-in rosters, hot work permits, and zero-tolerance drug/alcohol enforcement.
•Incident Escalation: Chain of command for immediate reporting of near-misses, injuries, structural damage, or municipal stop-work notices.

Log the meeting minutes, record attending trade companies and superintendents, and list all agreed jobsite logistics agreements here.

Write a note
5. Execute Pre-Mobilization Action Items

Complete all assigned operational tasks before clearing subcontractors to bring machinery or full labor crews onto the site.

Assign specific team owners and firm due dates to ensure zero regulatory or physical bottlenecks remain.

Add tasks
6. Authorize Site Mobilization & Trade Access

Issue the formal determination on site readiness for full trade mobilization.

Review the preceding verifications: temporary utilities energized, perimeter secured, SWPPP sediment controls trenched, OSHA compliance stations mounted, and trade kickoff orientations conducted.

Select the authorized site access level. Use the comment box to specify any conditional holdbacks (e.g., Site cleared for framing and excavation crews; mechanical rough-in staging restricted until east laydown pad gravel cures).

Choose one
  • 🟢 Full Mobilization Authorized (Unrestricted Site Access)
  • 🟡 Conditional Mobilization (Specific Trades Only)
  • 🔴 Site Mobilization Denied (Safety / Utility Hold)
04

🔄 Daily Execution & Quality Assurance Inspections

5 steps

Log your daily field operations, morning safety briefings, trade inspections, and photo documentation directly in this session. Your submissions create the verified chronological record of job site progress, subcontractor quality control, and pre-concealment sign-offs.

  1. 1

    🦺 Conduct Morning Toolbox Talk

  2. 2

    📋 Log Daily Site Conditions & Headcounts

  3. 3

    🔍 Audit In-Progress Trade Work

  4. 4

    📸 Verify Pre-Concealment Photo Records

  5. 5

    📌 Execute Daily Field Closeout Tasks

Read the full text
1. 🦺 Conduct Morning Toolbox Talk

Run the mandatory morning safety and production stand-up with all active trade foremen prior to work commencing.

Brief the specific high-risk operations scheduled for today (such as hot work, overhead lifting, trenching, or leading-edge fall protection), verify required Personal Protective Equipment (PPE) compliance across all crews, and confirm site logistics including crane delivery staging and material drop zones.

Select the primary safety focus addressed during this morning's briefing:

Choose one or more
  • 🦺 Fall Protection & Scaffolding
  • ⚡ Electrical Safety & Lockout/Tagout
  • 🚜 Trenching, Excavation & Heavy Equipment
  • 🔥 Hot Work, Fire Watch & Burn Permits
  • 🧤 PPE, Silica Dust & Chemical Handling
  • 📦 Overhead Hazards, Rigging & Crane Logistics
2. 📋 Log Daily Site Conditions & Headcounts

Record the official job site operational parameters to establish a verifiable legal and contractual record of daily site activity.

Capture the following operational baseline:

•Weather and site conditions: Note ambient temperature highs/lows, precipitation, wind conditions, and any adverse impacts to exterior operations (such as slab pours or roofing).
•Subcontractor trade headcounts: Document each trade contractor present on site along with the exact number of journeymen and apprentices deployed (e.g., Framing: 8, Electrical: 4, Plumbing: 3).
•Major deliveries & heavy equipment: Record bulk material deliveries received, ticket numbers, crane hours, lifts, or excavators active on site.
•Milestone progress: Detail the primary production accomplishments completed across building zones.

Provide your comprehensive daily operational notes below.

Write a note
3. 🔍 Audit In-Progress Trade Work

Inspect ongoing trade work against approved construction submittals, architectural and structural drawings, and manufacturer installation specifications.

Evaluate current installations across these core quality dimensions:

1.Dimensional tolerance: Verify rough opening clearances, wall plumbness, slab elevations, and sleeve locations.
2.Material compliance: Confirm that installed fixtures, rebar sizing, fasteners, insulation types, and pipe schedules match approved submittal cut sheets.
3.Manufacturer specifications: Check adherence to environmental requirements (such as curing temperature, sealants, lap splices, and mechanical fastening patterns).

Identify any deviations, non-conforming items, or defective workmanship. Record the trade responsible, grid line or room location, specific code/plan discrepancy, and the mandatory corrective action required within 24 hours.

Add notes
4. 📸 Verify Pre-Concealment Photo Records

Capture photographic proof of all mechanical, electrical, plumbing, structural framing, and waterproofing work before it is permanently concealed by insulation, drywall, backfill, or concrete pours.

High-resolution pre-concealment documentation prevents future warranty disputes and provides clear evidence of code compliance for municipal building inspectors and owners.

Upload clear photos of all in-wall rough-ins, above-ceiling mechanical rough-ins, under-slab conduits, and waterproofing membranes prior to sign-off. Ensure photos capture room markers, grid references, and backing plates.

Upload images
5. 📌 Execute Daily Field Closeout Tasks

Complete the end-of-day site protocol to ensure physical security, environmental compliance, and complete accountability before trade crews depart the property.

Assign and verify the mandatory end-of-day site handover items:

Add tasks
05

1.2. Compliance Review & Pre-Pour Checklist

2 steps
  1. 1

    Key Deliverables & Compliance Review

  2. 2

    Compliance: Pre-Pour Checklist

Read the full text
1. Key Deliverables & Compliance Review
Add tasks
2. Compliance: Pre-Pour Checklist

A 6-item visual gate executed on-site by the Field Superintendent via tablet:

Choose one or more
  • ✅ Underground plumbing pressure test passed ($150\,\text{psi}$ held for 30 minutes).
  • ✅ Electrical conduit sweeps and stub-ups verified against floor plans.
  • ✅ Rebar clearance (2 inches minimum from earth) and lap splash verified.
  • ✅ Formwork dimensioned, squared, and braced for hydrostatic concrete pressure.
  • ✅ Structural Engineer special inspection clearance signed.
  • ✅ Municipal building inspector signed the physical job-site permit card.
06

📅 1.3. Review Meeting (site walk)

5 steps
  1. 1

    Critical Items to Review During the Walk

  2. 2

    Concrete Truck Authorization: Is the site 100% cleared to call the concrete plant and confirm truck delivery times?

  3. 3

    Where do the pump trucks park, in what order are sections poured, and who is directing traffic/washouts?

  4. 4

    Additional notes.

  5. 5

    Decision Gate Sign-Off

Read the full text
1. Critical Items to Review During the Walk

Please go over this checklist.

Choose one or more
  • ✅ Excavation & Subgrade: Soil cleanliness (no mud, standing water, or debris in trenches) and compaction sign-off.
  • ✅ Formwork & Layout: Form lines, squareness, elevation datum points, and bracing stability to withstand concrete pressure.
  • ✅ Rebar & Structural Steel: Lap splices, rebar size/spacing, corner ties, and clearance chairs (ensuring rebar sits at least $2\text{ in}$ above earth).
  • ✅ Underground MEP Stub-ups: Location, plumbness, and elevation of plumbing drain pipes, water mains, and electrical conduits exiting the slab.
  • ✅ Sleeve & Penetration Locations: Utility wall sleeves and anchor bolt placement against architectural grids.
2. Concrete Truck Authorization: Is the site 100% cleared to call the concrete plant and confirm truck delivery times?
Choose one
  • Yes
  • No
3. Where do the pump trucks park, in what order are sections poured, and who is directing traffic/washouts?
Write a note
4. Additional notes.

If minor items fail (e.g., a missing rebar tie or displaced conduit), who fixes it, and is a photo sign-off permitted before the first truck arrives?

Add notes
5. Decision Gate Sign-Off
Choose one
  • 🔴 Hold — Engineering or Subgrade Failure
  • 🟡 Conditional Hold — Minor Fix Required (Re-Inspect before Pour)
  • 🟢 Approved — Permission to Pour Concrete Granted
07

2.3 Field Validation & Work Verification Checklist

4 steps

Inspect the building envelope, complete physical verification of roofing, waterproofing, windows, and framing, and log your field observations. Your verification determines whether the building is watertight and cleared for interior trade mobilization.

  1. 1

    Validate Roofing and Waterproofing Systems

  2. 2

    Verify Exterior Openings and Framing

  3. 3

    Upload Field Inspection Photos

  4. 4

    Issue Watertightness Gate Determination

Read the full text
1. Validate Roofing and Waterproofing Systems

Conduct a comprehensive physical walk of the roof deck and perimeter terminations before clearing trades beneath this scope.

Inspect every penetration, seam, and critical transition using the checklist criteria below:

•Check that membrane field seams, lap joints, and perimeter terminations are 100% heat-welded or sealed per manufacturer specifications with no fishmouths or voids.
•Confirm primary drains and overflow scuppers are cleared of construction debris, set at the lowest slab elevations, and clamped with proper ring compression.
•Ensure counter-flashing is securely embedded or reglet-mounted into exterior wall framing without exposed or unsealed fastener penetrations.
•Confirm completion of the 24-hour standing flood test or targeted hydrostatic spray test at all critical valley transitions without dampness or leaks on the underside deck.

Select all inspection checkpoints verified and sound. Note any punch items requiring remedial torch work or sealant in the comment box.

Choose one or more
  • ✅ Membrane seams and edge terminations inspected
  • 🌊 Roof drains and overflow scuppers clamped and clear
  • 🧱 Parapet counter-flashing embedded and sealed
  • 💧 Flood or hose spray test passed without leaks
2. Verify Exterior Openings and Framing

Inspect the exterior building envelope penetrations, drainage planes, and structural lateral framing prior to insulation or drywall loading.

Verify compliance with structural details and building science water-shedding principles:

•Confirm window sill pan flashings slope outward toward the exterior drainage plane with end dams intact and weep paths unobstructed.
•Inspect the weather-resistive barrier (WRB) to confirm proper shingling, continuous seam taping, and absence of tears or unsecured penetrations.
•Cross-check framing plans to ensure designated header sizes, hold-down anchors, hurricane ties, and shear wall nailing schedules match engineering specifications.

Mark each structural and weather-barrier requirement confirmed on site. Record any trade coordination conflicts or missed fasteners.

Choose one or more
  • 🪟 Window pan flashings sloped with clear weeps
  • 🛡️ Weather-resistive barrier shingled and taped
  • 🔩 Structural shear nailing and hold-downs verified
  • 🪵 Framing headers and hurricane clips inspected
3. Upload Field Inspection Photos

Provide date-stamped photographic verification of critical flashing details, flood testing water levels, window sill pans, and shear wall nailing.

High-resolution visual evidence serves as permanent quality documentation for the project closeout file, design team review, and warranty validation.

Upload your site inspection images or manufacturer inspection sign-off sheets directly here.

Upload images
4. Issue Watertightness Gate Determination

Evaluate the cumulative field observations, water testing results, and framing checks to issue the formal envelope milestone determination.

Selecting a status establishes trade readiness:

•🔴 Hold: Active leaks detected during water testing or structural framing deficiencies exist; interior moisture-sensitive trades remain halted.
•🟡 Conditional Approval: Assembly is dry and framing is structurally approved, but isolated flashing touch-ups or tape patches must finish within 48 hours.
•🟢 Approved: Envelope is verified 100% watertight and framing is fully signed off; interior trades (insulation, drywall, MEP rough-in closeout) are authorized to proceed.

Select the project status and document your superintendent sign-off notes and required follow-up deadlines in the rationale comment.

Choose one
  • 🔴 Hold — Envelope Leaks or Framing Defect
  • 🟡 Conditional Approval — Minor Touch-Ups Required
  • 🟢 Approved — Building Watertight and Cleared
08

📅 2.1 Trade Handoff Meeting

2 steps
  1. 1

    On-site walkthrough Agenda

  2. 2

    Notes

Read the full text
1. On-site walkthrough Agenda
Choose one or more
  • Roofing & Envelope Handoff: Trade foreman presents finished roof membrane, flashing, drains, and exterior wall wraps.
  • Critical Transitions: Review complex joints (roof-to-wall flashing, window pan flashing, skylight curbs).
  • Outstanding Scope: Identify any open trim or temporary sealant details before water testing.
2. Notes
Add notes
09

2. Sub Document Request

5 steps

Submit your complete roofing warranty package, technical cut sheets, notice of completion, and executed self-inspection QA checklist. Our project engineering and superintendent team will review your submittals to verify compliance and determine readiness for the punch walk and final closeout handoff.

  1. 1

    📄 Upload Roofing Warranty Documents

  2. 2

    📝 Submit Notice of Completion

  3. 3

    ✅ Upload Signed QA Self-Inspection

  4. 4

    🔍 Audit Closeout Documentation

  5. 5

    ⚖️ Determine Submittal Package Status

Read the full text
1. 📄 Upload Roofing Warranty Documents

Upload the formal manufacturer warranty certificate, contractor workmanship warranty, and technical product cut sheets for all installed roofing materials.

Ensure the warranty package explicitly reflects:

•Manufacturer system warranty coverage terms, duration (e.g., 20-year NDL), and exact membrane specifications.
•Approved technical cut sheets and material data sheets showing ASTM compliance for field membranes, base flashing, adhesive, fasteners, and counter-flashing metals.
•Executed contractor workmanship warranty countersigned by an authorized corporate officer.

Attach all PDF documents below.

Upload files or add links
2. 📝 Submit Notice of Completion

Submit the signed and notarized Notice of Completion for all contracted roofing and waterproofing scope.

Before uploading, verify the following details:

•Exact legal description and project address match contract documents.
•Specified date of substantial completion for the roofing system.
•Confirmation that all primary membrane seams, perimeter copings, counter-flashings, and roof penetration boots are fully finished and cleared of debris.

Upload the signed document file directly below.

Upload files or add links
3. ✅ Upload Signed QA Self-Inspection

Upload your completed and signed Roofing Subcontractor Quality Assurance / Quality Control Self-Inspection checklist.

In accordance with project quality standards and field validation requirements, your self-inspection record must show:

•Verification of all perimeter terminations, parapet flashing, counter-flashing details, and expansion joints.
•Inspection of primary roof drains, clamping rings, and overflow scuppers confirming clear drainage and unobstructed flow.
•Logged results of the standing water flood test (minimum 24 hours) or hydrostatic spray tests conducted at critical valley and flashing transitions.
•Daily sign-offs and supervisor signature certifying zero open penetrations or active defects.

Upload the scanned or digital inspection record below.

Upload files or add links
4. 🔍 Audit Closeout Documentation

Verify that the subcontractor's submittal package meets all project specifications, manufacturer warranty prerequisites, and contract requirements.

Evaluate the submitted package against these four criteria:

•Warranty Authenticity: Manufacturer warranty reflects exact project square footage, system specifications, and manufacturer inspection sign-off.
•Specification Alignment: Cut sheets match submittal register approvals and installed assemblies.
•Legal & Contractual Execution: Notice of Completion is properly dated, notarized, and aligned with site progress.
•Field Verification Quality: Self-inspection confirms completed flood or hydrostatic testing and watertight perimeter terminations.

Document any missing attachments, discrepancies, or technical exceptions in your notes below.

Add notes
5. ⚖️ Determine Submittal Package Status

Evaluate the roofing trade's submitted warranty package and select the formal determination.

Choose the applicable review determination based on package completeness:

•If required attachments, testing logs, or signatures are absent, select the awaiting status to prompt immediate trade resubmission.
•If all submittals, warranties, cut sheets, and testing certifications are verified and accepted, select the ready status to clear the submittal package and proceed to the site walkthrough.

Provide your review findings, outstanding conditions, or next meeting instructions in your comment.

Choose one
  • ⏳ Incomplete - Awaiting Trade Handoff Docs
  • 🚀 Ready - Package Approved & Walkthrough Scheduled
10

3.1 Document Request Gate

5 steps

Add all required municipal rough certificates, trade pressure test logs, and approved in-wall change orders directly into the project folder. Complete each verification check below to confirm all documentation has been audited prior to authorizing drywall and wall concealment.

  1. 1

    Create a main folder for the following documents

  2. 2

    📁 File Municipal Rough Certificates

  3. 3

    📁 File Hydrostatic & Pressure Logs

  4. 4

    📁 File In-Wall Change Orders

  5. 5

    📋 Release Wall Concealment Clearance

Read the full text
1. Create a main folder for the following documents

Add link below

Upload files or add links
2. 📁 File Municipal Rough Certificates

Ensure signed municipal building inspection cards are fully verified and added directly to the official project document folder under MEP Rough-Ins.

Every jurisdiction requires explicit sign-offs before any wall cavities are closed. Audit each permit card for an official inspector signature, date, and unconditional "Pass" status across:

•Building / Framing: Structural framing, fire-blocking, draft-stopping, and nail plates.
•Electrical Rough: Conduits, boxes, grounding, and wiring runs before insulation.
•Plumbing Rough: DWV piping, water distribution rough-in, and gas piping.
•Mechanical Rough: Duct runs, exhaust terminations, venting, and refrigerant lines.

Confirm that all four cards are verified and added to the folder.

Choose one
  • ✅ All 4 rough certificates verified and in folder
  • ⚠️ Partial pass (conditional reinspection required)
  • ❌ Missing municipal inspector sign-offs
3. 📁 File Hydrostatic & Pressure Logs

Verify that all specialized trade pre-concealment test logs are completed, signed by trade foremen, and placed into the project document folder.

Concealing unverified pressure lines creates severe water damage and air leakage risks behind finished drywall. Check that the uploaded documentation includes:

•Hydrostatic Plumbing Test: Domestic water and DWV lines held under designated static pressure for the required inspection window without gauge drop.
•HVAC Duct Air Balance & Leakage: Pre-test logs validating duct seam sealing and compliance with CFM specifications.
•Gas Piping Pressure Test: 24-hour gauge pressure log witnessed and verified.

Verify the test certificates and log your confirmation below.

Choose one
  • ✅ Hydrostatic & duct pressure logs verified in folder
  • ⚠️ Test logs incomplete or missing foreman signature
  • ❌ Test failures recorded (re-test pending)
4. 📁 File In-Wall Change Orders

Verify that all scope adjustments, owner changes, and field condition revisions inside wall assemblies are fully costed, approved, and filed in the project folder.

Drywalling over unauthorized or unpriced in-wall rough-ins leads to unrecoverable backcharges and rework disputes. Ensure:

•All trade contractor field work tickets are cross-referenced against approved Change Orders (COs).
•The Project Manager has formally executed pricing and schedule adjustments for added conduit, relocated rough-ins, or supplemental framing.
•No contested or unapproved rough-in work remains inside open cavities.

Confirm change order documentation status before proceeding to trade release.

Choose one
  • ✅ All in-wall change orders approved and in folder
  • ⚠️ Open change directives pending PM cost sign-off
  • ℹ️ No in-wall change orders on this phase
5. 📋 Release Wall Concealment Clearance

Review the status of municipal certificates, trade pressure tests, and approved change orders in the project folder to issue the final drywall authorization.

Execute the following verification checklist before releasing drywall crews into the zone:

Add tasks
11

📅 3.2 Trade Handoff Meeting

2 steps
  1. 1

    On-site Walkthrough Agenda

  2. 2

    Notes

Read the full text
1. On-site Walkthrough Agenda
Choose one or more
  • A — Trade Coordination Walk: Lead walkthrough with MEP foremen to confirm ductwork, piping, and wiring home-runs do not clash or block light fixtures.
  • B — Structural Penetration Review: Verify no trade notched or bored load-bearing studs, floor joists, or truss webs outside engineering specs.
  • C — Architectural Backing Verification: Confirm wood/metal backing is installed for wall-hung cabinets, TV mounts, grab bars, and door stops.
2. Notes
Add notes
12

3.3 Physical Field Validation

5 steps

Inspect all open wall bays, ceiling cavities, and MEP rough-ins before sheetrock hanging begins. Complete the verification checkpoints, upload as-built cavity scans, and issue the pre-drywall sign-off to ensure zero concealment non-conformances.

  1. 1

    📋 Verify Municipal Rough Sign-Offs

  2. 2

    🛡️ Audit Penetrations and Mechanical Protection

  3. 3

    📸 Capture Cavity As-Built Media

  4. 4

    ⚠️ Log Pre-Drywall Punch Items

  5. 5

    🚦 Authorize Pre-Drywall Close-In

Read the full text
1. 📋 Verify Municipal Rough Sign-Offs

Confirm all required jurisdictional inspections have been officially signed off and posted on-site before authorizing drywall stocking or hanging.

Review the physical permit card and municipal inspection portal to confirm zero open re-inspection notices:

•Plumbing rough-in: Supply lines under static pressure test (water or air) with zero drop over the specified inspection duration; drain-waste-vent (DWV) head tests passed.
•Mechanical / HVAC rough-in: Duct leakage testing complete, exhaust terminations flanged, refrigerant lines brazed and pressure-tested, condensate drains sloped.
•Electrical rough-in: Grounding electrode system verified, neutral/ground isolation maintained, all box volumes compliant with NEC fill calculations, arc-fault/ground-fault pathways mapped.
•Framing & structural rough-in: Shear wall nailing inspected, hold-downs torqued, truss bracing anchored, fireblocking/draftstopping approved by the building inspector.

Check each municipal discipline verified on the official inspection card. Use the comment box to record permit numbers and inspector sign-off dates.

Choose one or more
  • ⚡ Electrical rough passed & signed
  • 💧 Plumbing rough passed & signed
  • ❄️ Mechanical/HVAC rough passed & signed
  • 🪵 Framing structural rough passed & signed
2. 🛡️ Audit Penetrations and Mechanical Protection

Walk every open stud bay and plenum track to verify physical protection against mechanical puncture and fire/smoke migration.

Apply these code and quality standards:

1.Fire-stopping & draft-stopping: Ensure approved intumescent firestop sealant (red/gray) or mineral wool safing is installed around all annular spaces where piping, conduit, or cabling penetrates fire-rated assemblies, top plates, or floor decks. Verify zero annular voids or unsealed chase gaps.
2.Nail safety strike plates: Confirm heavy-gauge steel nail plates are installed on all wood or light-gauge metal studs where wiring, flexible gas tubing, or plumbing pipes pass within 1.25 inches (32 mm) of the stud face.
3.Piping & wire routing: Ensure cables are supported within 12 inches of each enclosure and secured with approved insulated staples. Confirm zero cross-contact between dissimilar metals (e.g., copper touching galvanized studs).

Select the safety and penetration controls confirmed in the field. Add notes detailing any bays requiring trade back-check.

Choose one or more
  • 🔥 Fire-stopping sealed at all floor/ceiling penetrations
  • 🧱 Mineral wool draft-stopping complete in chases
  • 🛡️ Steel nail plates installed on all offset routings (<1.25 in)
  • 🔌 Cabling secured and protected from sharp metal edges
3. 📸 Capture Cavity As-Built Media

Upload complete 360-degree photo or video documentation of all open wall cavities, chases, and ceiling rough-ins prior to drywall hanging.

Documenting pre-concealment conditions provides permanent as-built evidence for facility management, future tenant improvements, and warranty defect defense.

Ensure your visual captures include:

•Clear room and gridline orientation markers (e.g., photo of unit number/room label before cavity walk).
•High-resolution framing-to-cavity views showing pipe drops, junction boxes, low-voltage bundles, blocking, and in-wall carrier brackets.
•Detailed elevation views of specialty backing (TV mounts, grab bars, heavy millwork grounds).

Upload the full room scan video files, photo log, or direct cloud links to the 360-degree capture repository below.

Upload files or add links
4. ⚠️ Log Pre-Drywall Punch Items

Record any deficiencies, unverified rough-ins, or damage caused by adjacent trades that must be rectified before hanging sheetrock.

Use this format for each logged observation:

•Location: Grid line, room number, wall orientation (e.g., Unit 302, Master Bath East Wall).
•Subcontractor responsible: Electrical, Mechanical, Plumbing, Framing, or Fire Protection.
•Deficiency description: Specific issue (e.g., missing nail plate at PEX drop, unsealed 2-inch conduit penetration at ceiling plate).
•Required action & timeline: Clear corrective directive and re-inspection cutoff.

Post each punch item as an entry below. React with 🔧 when corrective work is underway, and ✅ once reinspected and verified clear.

Add notes
5. 🚦 Authorize Pre-Drywall Close-In

Evaluate total rough-in inspection compliance and determine whether interior trades are authorized to hang drywall and conceal cavities.

Make your final field authorization based on the criteria below:

•Approved for Drywall: All 4 municipal roughs passed, penetration firestopping complete, nail strike plates 100% verified, 360-degree cavity capture uploaded, and zero open critical punch items.
•Conditional Approval: Minor trade corrections required (e.g., adding 2 nail plates or sealing a single chase) that can be cleared and re-inspected within 4 hours prior to sheetrock hanging.
•Hold / Concealment Blocked: Missing municipal inspection sign-off, structural defects, failed pressure tests, or unverified MEP rough-ins. No sheetrock may be hung.

Select the project status and provide your sign-off rationale in the comments.

Choose one
  • 🟢 Approved for Drywall: Cavities released for full hang
  • 🟡 Conditional Approval: Specific minor items cleared prior to hang
  • 🔴 Hold: Concealment blocked until reinspection
13

4.1 Document Request Gate

2 steps
  1. 1

    Internal tasks

  2. 2

    📄 Upload Closeout & Certificate of Occupancy Documents

Read the full text
1. Internal tasks
Add tasks
2. 📄 Upload Closeout & Certificate of Occupancy Documents

Upload the architectural punch list, third-party balancing/commissioning reports, and the municipal Certificate of Occupancy prior to final owner sign-off.

Add tasks
14

📅 4.2: Trade Handoff Meeting

2 steps
  1. 1

    On-site Walkthrough Agenda

  2. 2

    Notes

Read the full text
1. On-site Walkthrough Agenda
Choose one or more
  • A — Architect Punch List Walk: Walk every room with the Architect and Client Representative to log cosmetic and finish deficiencies.
  • B — Owner System Demonstration: Conduct operational handoff walk showing client facility staff how to operate main disconnects, HVAC thermostats, and water shutoffs.
  • C — Final Financial & Scope Alignment: Review completed change orders, retainage release requirements, and warranty binder delivery dates
2. Notes
Add notes
15

4.3 Physical Field Validation

5 steps

Complete this final acceptance walk with the Architect and Owner to verify full operational readiness, life-safety clearance, and turnover compliance. Work through each verification gate below and log the final substantial completion punch status for occupancy handoff.

  1. 1

    📋 Verify Closeout Punch Status

  2. 2

    🚒 Inspect Life-Safety & Regulatory Clearance

  3. 3

    ⚙️ Commission MEP Systems & Finishes

  4. 4

    🔑 Transfer Turnover Assets & Documentation

  5. 5

    📝 Issue Substantial Completion Certificate

Read the full text
1. 📋 Verify Closeout Punch Status

Conduct the final interior walk with the Project Architect to review all architectural punch list items.

Inspect finishes, casework, door hardware adjustments, paint touch-ups, and acoustic ceiling tiles across all building zones. Ensure all previously identified deficiency items are physically resolved to architectural specification standards.

Confirm that the Architect of Record has performed their walkthrough inspection and countersigned the final substantial completion punch list.

Choose one
  • 📋 Architect punch list 100% signed off
  • ⚠️ Minor cosmetic backcheck pending
  • 🛑 Open architectural deficiencies unresolved
2. 🚒 Inspect Life-Safety & Regulatory Clearance

Verify operational testing and life-safety systems clearance with the local authority having jurisdiction (AHJ) and MEP engineers.

Check that all life-safety and emergency egress paths meet code requirements:

•Fire alarm system tested, monitored, and certified by the central station.
•Emergency egress lighting and exit signage tested under battery backup power.
•Sprinkler head coverage aligned with finished ceiling layout and escutcheons in place.
•Panic hardware, magnetic hold-opens, and fire-rated door assemblies latched and functional.
•Formal Certificate of Occupancy (CO) or Temporary Certificate of Occupancy (TCO) physically issued and posted.

Select the operational verification status confirmed during the site walk and note any pending inspector backchecks.

Choose one or more
  • 🚒 Fire alarm & life-safety operational
  • 📜 Certificate of Occupancy issued
  • ⏳ TCO active with conditional terms
  • 🛑 Life-safety inspection pending re-test
3. ⚙️ Commission MEP Systems & Finishes

Inspect mechanical, electrical, plumbing, and low-voltage installations to verify full operating condition.

Walk all plant rooms and occupied tenant zones to confirm:

•HVAC units balanced (Test and Balance report verified), filters replaced, and thermostats calibrated.
•Plumbing fixtures tested for hot/cold supply, drainage, flush volume, and leak-free traps.
•Electrical panels balanced, indexed with typed directories, and cover plates installed.
•Final interior deep clean complete, including window glazing, hard surface waxing, and carpet vacuuming.

Attach the completed MEP commissioning punch report and TAB certification log.

Upload files or add links
4. 🔑 Transfer Turnover Assets & Documentation

Confirm all contractual handoff packages, owner operation assets, and warranties are transferred to the Owner's facility management team.

Verify physical receipt and digital transmission for the following turnover items:

•Grand master keying schedule, tagged brass keys, and re-programmed access cards.
•Final Operation & Maintenance (O&M) manuals, equipment cut sheets, and asset tags.
•Executed manufacturer and general contractor warranty agreements.
•24/7 emergency subcontractor contact roster for active warranty response.

Select all items delivered and accepted during the joint turnover transfer.

Choose one or more
  • 🔑 Keys, O&M manuals & warranties delivered
  • 🔐 Electronic access control permissions transferred
  • ☎️ 24/7 Emergency trade response list verified
  • 🛑 Owner asset turnover incomplete
5. 📝 Issue Substantial Completion Certificate

Record the official substantial completion outcome and log any minor owner backcheck stipulations agreed during the joint acceptance walk.

Review the standard criteria for formal occupancy handoff:

1.Building is legally approved for intended occupancy (CO/TCO in hand).
2.Remaining punch items are non-critical, cosmetic items that do not impede normal owner operations.
3.Building operations and utility meters are officially scheduled for owner utility transfer.

Draft the final substantial completion verification summary in the space below, incorporating:

•Date of substantial completion walk and attendees (Owner, Architect, General Contractor).
•Agreed monetary value and 14-day completion deadline for any remaining punch items.
•Final determination on warranty start date and property insurance transfer.
Write a note
16

Incident Response & Log

4 steps

Follow this response workflow immediately upon discovering or being notified of a jobsite safety, structural, or environmental incident. Review the escalation protocols, classify the incident severity, and complete initial notifications and scene containment to protect personnel and secure the site.

  1. 1

    🚨 Classify Incident and Emergency Route

  2. 2

    📝 Log Incident Chronology and Scene Facts

  3. 3

    📸 Upload Scene Photos and Physical Evidence

  4. 4

    🛡️ Execute Immediate Containment Actions

Read the full text
1. 🚨 Classify Incident and Emergency Route

Triage the scene immediately and identify the exact severity level of the incident. Ensuring human life safety and stopping immediate danger always takes precedence over administrative reporting.

Select the incident category that represents the event. In the comment field, record the exact time the event occurred and confirm whether emergency services (911) have been dispatched.

Choose one or more
  • 🚑 Tier 1: Critical Medical or Life-Threatening Emergency
  • 🏗️ Tier 1: Structural Collapse or Major Rigging Failure
  • ⚡ Tier 1: Active Gas Leak or High-Voltage Utility Strike
  • 🏥 Tier 2: Non-Life-Threatening OSHA Recordable Injury
  • 🛢️ Tier 2: Environmental Chemical, Fuel, or Hazmat Spill
  • 🚧 Tier 2: Subsurface Utility Strike or Water Main Breach
  • 🩹 Tier 3: Minor First Aid Incident (Return to Work)
  • ⚠️ Tier 3: Safety Near Miss (No Injury or Property Loss)
  • 🔨 Tier 3: Minor Tool, Vehicle, or Property Damage
2. 📝 Log Incident Chronology and Scene Facts

Record the objective facts of the incident while details are fresh. Stick strictly to physical evidence, observed actions, and verified facts without assigning personal blame or speculating on causes.

Structure your initial incident statement using this four-part standard:

•Who: Name of injured or involved individuals, trade employer/subcontractor, and eyewitnesses present.
•Where: Exact grid line, floor level, room designation, or exterior site elevation where the incident took place.
•What: Specific equipment, materials, tools, or environmental factors directly involved in the occurrence.
•Initial Action: Immediate actions taken at the scene (e.g., first aid applied, valve shut off, electrical breaker pulled, emergency services routed).

Add your completed incident statement below.

Write a note
3. 📸 Upload Scene Photos and Physical Evidence

Upload clear, high-resolution photographs documenting the incident area and surrounding physical environment before any disturbance occurs.

Capture the scene using the following three perspectives:

•Wide Angle: Full context of the work zone, visible safety signage, weather conditions, barricades, and site lighting.
•Mid-Range: Relative position of tools, equipment, materials, and safety controls in relation to permanent structure.
•Close-Up: Specific point of failure, damaged equipment labels, broken rigging hardware, PPE condition, or fluid leaks.

Upload all relevant photos, sketches, or inspection slips directly here.

Upload files or add links
4. 🛡️ Execute Immediate Containment Actions

Assign and track the mandatory containment and regulatory notification actions required for this incident level. Every action item must have a designated owner and be completed before active construction resumes in the impacted zone.

Confirm that each essential containment task is assigned and executed:

Add tasks
17

Warranty ticket

15 steps

Submit your warranty service request and defect documentation for review during your 1-year post-occupancy warranty period. Provide the location, affected trade system, photographic evidence, and access availability so our warranty management team can evaluate coverage and coordinate corrective trade work.

  1. 1

    Identify the specific room and location

  2. 2

    Select the affected building trade or system

  3. 3

    Select the urgency and severity level

  4. 4

    Detail the defect symptoms and chronology

  5. 5

    Upload photo and video evidence

  6. 6

    Specify site access availability and site contacts

  7. 7

    Trade Contact / Warranty Routing Options

  8. 8

    Trade Contact / Warranty Routing Options

  9. 9

    Trade Contact / Warranty Routing Options

  10. 10

    Trade Contact / Warranty Routing Options

  11. 11

    Trade Contact / Warranty Routing Options

  12. 12

    Trade Contact / Warranty Routing Options

  13. 13

    Trade Contact / Warranty Routing Options

  14. 14

    Trade Contact / Warranty Routing Options

  15. 15

    Subcontractor Back-Charge & Enforcement: Automatically routing warranty items back to the responsible trade contractor.

Read the full text
1. Identify the specific room and location

Pinpoint the exact location of the issue within the building.

Provide:

•Building, floor, and suite/room number
•Specific surface or element: (e.g., northeast ceiling corner, under lavatory P-trap, exterior curtain wall mullion at grid line B-4)
•Operational impact: Whether this location can remain occupied or if operations must be temporarily paused around the affected area
Write a note
2. Select the affected building trade or system

Indicate which building system or trade package is experiencing the defect. Accurate categorization routes your request directly to the appropriate subcontractor warrantor under their original contract scope.

Choose one
  • 💧 Plumbing & Domestic Water
  • ⚡ Electrical, Lighting & Low Voltage
  • ❄️ HVAC, Controls & Air Distribution
  • 🪟 Windows, Doors, Glazing & Hardware
  • 🧱 Finishes: Drywall, Paint & Millwork
  • 🪵 Flooring, Tile & Baseboards
  • 🛡️ Roofing, Flashing & Waterproofing
  • 🏢 Structural Framing & Concrete
3. Select the urgency and severity level

Classify the operational severity of the condition. Selecting an accurate severity level ensures emergency response protocols activate immediately for active hazards while non-critical cosmetic items are scheduled efficiently.

Choose one
  • 🚨 Emergency: Active leak, power loss, or life-safety hazard
  • ⚠️ Urgent: Loss of heating/cooling or room unserviceable
  • 🟡 Standard: Operational defect with workarounds available
  • ⚪ Cosmetic: Surface finish, paint touch-up, or minor trim
4. Detail the defect symptoms and chronology

Describe the observed defect, when it first appeared, and how the condition has developed over time. Use this reporting structure:

•First observed: Date and time the condition was initially noticed.
•Triggering conditions: Note any correlated events (e.g., occurred during heavy rainfall, after breaker trip, when mechanical unit engaged).
•Physical symptoms: Describe sounds, odors, visible moisture, thermal variance, or mechanical binding.
•Containment steps taken: Detail temporary measures enacted on site (e.g., catch buckets placed, isolated breaker turned off, zone valve closed).
Write a note
5. Upload photo and video evidence

Provide clear photographic and video evidence documenting the defect. Quality visual documentation enables the warranty team and responsible trade contractors to diagnose root causes and bring appropriate replacement parts before the site visit.

Follow standard forensic photo verification practices:

•Wide-angle perspective: Capture the overall room or envelope context showing where the defect sits relative to known architectural reference points.
•Mid-range perspective: Frame the assembly or equipment showing adjacent connections, penetrations, or joints.
•Close-up detail: Capture sharp, well-lit images of the specific defect, crack, water stain, or equipment diagnostic code.

Upload all high-resolution images or short video clips showing the issue under operating conditions.

Upload files or add links
6. Specify site access availability and site contacts

Provide on-site access instructions and primary point-of-contact details to streamline repair scheduling with trade subcontractors. Detail:

•Primary on-site contact: Name, direct phone number, and email.
•Preferred access windows: Days of the week and operating hours when trades can access the work area without disrupting building operations.
•Site check-in rules: Security badges, escort requirements, PPE regulations, or loading dock restrictions.
Write a note
7. Trade Contact / Warranty Routing Options

Click here if you have already contacted this trade and automatically routed the warranty items back to them

Choose one
  • 💧 Plumbing & Domestic Water
  • 💧 Plumbing & Domestic Water
  • 💧 Plumbing & Domestic Water
  • 💧 Plumbing & Domestic Water
  • 💧 Plumbing & Domestic Water
  • 💧 Plumbing & Domestic Water
8. Trade Contact / Warranty Routing Options

Click here if you have already contacted this trade and automatically routed the warranty items back to them

Choose one
  • ⚡ Electrical, Lighting & Low Voltage
  • ⚡ Electrical, Lighting & Low Voltage
  • ⚡ Electrical, Lighting & Low Voltage
  • ⚡ Electrical, Lighting & Low Voltage
  • ⚡ Electrical, Lighting & Low Voltage
  • ⚡ Electrical, Lighting & Low Voltage
9. Trade Contact / Warranty Routing Options

Click here if you have already contacted this trade and automatically routed the warranty items back to them

Choose one
  • ❄️ HVAC, Controls & Air Distribution
  • ❄️ HVAC, Controls & Air Distribution
  • ❄️ HVAC, Controls & Air Distribution
  • ❄️ HVAC, Controls & Air Distribution
  • ❄️ HVAC, Controls & Air Distribution
  • ❄️ HVAC, Controls & Air Distribution
10. Trade Contact / Warranty Routing Options

Click here if you have already contacted this trade and automatically routed the warranty items back to them

Choose one
  • 🪟 Windows, Doors, Glazing & Hardware
  • 🪟 Windows, Doors, Glazing & Hardware
  • 🪟 Windows, Doors, Glazing & Hardware
  • 🪟 Windows, Doors, Glazing & Hardware
  • 🪟 Windows, Doors, Glazing & Hardware
  • 🪟 Windows, Doors, Glazing & Hardware
11. Trade Contact / Warranty Routing Options

Click here if you have already contacted this trade and automatically routed the warranty items back to them

Choose one
  • 🧱 Finishes: Drywall, Paint & Millwork
  • 🧱 Finishes: Drywall, Paint & Millwork
  • 🧱 Finishes: Drywall, Paint & Millwork
  • 🧱 Finishes: Drywall, Paint & Millwork
  • 🧱 Finishes: Drywall, Paint & Millwork
  • 🧱 Finishes: Drywall, Paint & Millwork
12. Trade Contact / Warranty Routing Options

Click here if you have already contacted this trade and automatically routed the warranty items back to them

Choose one
  • 🪵 Flooring, Tile & Baseboards
  • 🪵 Flooring, Tile & Baseboards
  • 🪵 Flooring, Tile & Baseboards
  • 🪵 Flooring, Tile & Baseboards
  • 🪵 Flooring, Tile & Baseboards
  • 🪵 Flooring, Tile & Baseboards
13. Trade Contact / Warranty Routing Options

Click here if you have already contacted this trade and automatically routed the warranty items back to them

Choose one
  • 🛡️ Roofing, Flashing & Waterproofing
  • 🛡️ Roofing, Flashing & Waterproofing
  • 🛡️ Roofing, Flashing & Waterproofing
  • 🛡️ Roofing, Flashing & Waterproofing
  • 🛡️ Roofing, Flashing & Waterproofing
  • 🛡️ Roofing, Flashing & Waterproofing
14. Trade Contact / Warranty Routing Options

Click here if you have already contacted this trade and automatically routed the warranty items back to them

Choose one
  • 🏢 Structural Framing & Concrete
  • 🏢 Structural Framing & Concrete
  • 🏢 Structural Framing & Concrete
  • 🏢 Structural Framing & Concrete
  • 🏢 Structural Framing & Concrete
  • 🏢 Structural Framing & Concrete
15. Subcontractor Back-Charge & Enforcement: Automatically routing warranty items back to the responsible trade contractor.

Add follow-up tasks to ensure this issue is managed properly and keep all action details in one place.

Add tasks